We started a job last November for mold removal and we still have not been paid on the work we did so now I want to excerise our lien rights onthis job

2 replies

Apr 18, 2022

Lawsuits must be filed on a lien within 90 days after it is recorded.

Sometimes a subsequent lien may be recorded if a prior one has expired.

0 people found this helpful
Helpful
Apr 18, 2022

If you are performing construction related work, you may have rights to record a lien against the property and file suit to enforce the lient and your contract.

0 people found this helpful