What will happen if I have filed a lien after the 90 day period has passed?

FloridaLien Deadlines

I though the deadline for filing in lien in Florida was 90 days after the NTO was sent. I have filed 13 lien and now have realized that we have surpassed the 90 day period of furnishings.

1 reply

Jul 9, 2021
There is no connection between the service of the NTO and the filing date of a construction lien. You have 90 days from completing your work, not including punch-out, to file a lien.