What is the timetable for filing a lien in NV?

Nevada

After we have completed work, what is the timetable for filing a lien in NV? I know it is built into the LevelSet system, but we want the details so we understand.

2 replies

Jan 7, 2022

Generally speaking, in Nevada, the deadline to file a mechanics lien is within 90 days of either: (1) the completion of the work of improvement, or (2) the last date of furnishing labor and/or materials by the lien claimant; whichever is later.

However, this 90-day period may be shortened. If a Notice of Completion is filed and served, the deadline to file the lien claim is just 40 days from when the notice was served.

On residential projects, a Notice of Intent to Lien must be served on the owner at least 15 days prior to recording the lien itself. The service of this notice extends the time for filing the lien by 15 days.

More info from Levelset is here: https://www.levelset.com/mechanics-lien/nevada-lien-law-faqs/

2 people found this helpful
Helpful
Jan 7, 2022

Thank you for taking the time to respond!

0
Report Spam