We have filed the 2 month and third month notices. They have not paid yet (past 90 days). However we had extended them 90 day terms. If we need to file a claim, what are the parameters. Invoiced for material in April 2020. Have not received any payments to date. Project is a two year project for the contractor. We are working with the general contractor. We are still expecting to get paid however I wanted to know the limits as to when we can file a claim on the Bond