What does this mean in me as a contractor in my contract?

LouisianaConstruction Contract

However, in the event that Owner temporarily halts the work, Owner assumes any and all liability and responsibility for any and all costs associated with, related to, and/or arising from the work delay including, but not limited to, wages, loss of income, start-up costs, sub-contractor charges, additional trip charges, delayed material delivery charges, and material loss charges. Owner further understands and agrees that these charges may, at Contractor’s option, be deemed and considered to be extra work and be due and payable as extra work in accordance with the payment schedule below. The parties agree that Owners will only be allowed in the work area when accompanied by Contractor.