I'm a general contracting who uses sub-contractors on projects. We are not always aware of the suppliers they use to pick up or drop materials on project sites. Generally their accounts with suppliers are net 30 day accounts. In most cases completion of work and their invoices for payment are received prior to their suppliers requiring payment from them. In instances where they don't or can't provide us with a material release, is it good practice to hold their payment for 20 from their last day of work? Do their suppliers continue to have lien rights? If not what is the best way to manage this. Thank you Diane

1 reply

Feb 20, 2021

Hi Diane,

If the material release is a condition of payment, then you should be able to withhold payment until you receive it. If not, then you need to make payments promptly after receiving payment from the owner. Much of this depends on what your subcontract says. Happy to discuss more if you would like. My direct line is: 213.926.1516. Best regards, Greg 

0 people found this helpful
Helpful