Menu
Home>Levelset Community>Legal Help>Should we file a lien?

Should we file a lien?

Arizona

We are a sub-sub and have completed our portion of a very large commercial project. The project is ongoing, can we file a lien after the Notice of Completion is filed even though that will be more than 120 days since we finished our portion? Which was material supplier only no install.

1 reply

Oct 13, 2021

Fortunately, the "completion date" for lien purposes in Arizona is not dependant on when a subcontractor completes their portion of the work and focuses on when all work is complete under the master contract. Completion is defined by Arizona statute as the earliest of:

 1 Thirty days after final inspection and written final acceptance by the governmental body which issued the building permit for the building, structure or improvement.

2. Cessation of labor for a period of sixty consecutive days, except when such cessation of labor is due to a strike, shortage of materials or act of God. 

Thus, if the project is still ongoing, even if your portion is done, then under the law, there isn't a completion date yet.

Because the project is likely not yet "completed" under the law, you might be able to file a lien, but only if you properly served a preliminary 20-day notice as required by ARS 33-992.01. You should consult a construction attorney to review your notice and determine whether you have completed all requirements to filing a valid lien. 

0 people found this helpful
Helpful