Menu
Home>Levelset Community>Legal Help>Revision to progress payment schedule

Revision to progress payment schedule

California
Kim Collins
Office Manager at Bros Collins

We need to revise our remaining payment schedule because of schedule changes to the remaining work. No change order to final project total. Do we need to update our contract to reflect these changes (much like we do on a change order)? Thanks!

3 replies

Partner at Flores Ryan, LLP
| 280 reviews
Jun 22, 2022

This would still technically be a considered a change order. Best practice would be to submit a wirtten change order outling the new payment schedule and the reason for the changes. 

Do not act on the information contained herein without seeking the advice of licensed counsel. The information presented here is general in nature and is not
intended nor should be construed as legal advice for any particular case or client. The law is complex and the specific facts of your situation can cSee More...
See More...
2 people found this helpful
Helpful
hip poo
Jun 23, 2022
paper minecraft According to the contract, if you don't pay the fine, it's too horrible
0
Report Spam
Mia Read
N/A at N/A
Aug 16, 2023

I hope this message finds you well. I am writing to inform you about
some adjustments needed in our remaining payment schedule due to recent
changes in the project's work schedule. I'd like to emphasize that these
modifications will not impact the final project total, and there won't
be any alteration to the agreed-upon amount. [aarp mahjongg solitaire](https://aarpmahjonggsolitaire.com)

0
Report Spam