Menu
Home>Levelset Community>Legal Help> question on Lump Sum Contract as follows: In case during the project, there is one unexecuted item, is the owner in p

question on Lump Sum Contract as follows: In case during the project, there is one unexecuted item, is the owner in p

AlabamaConstruction Contract

Dear Sirs, I have one question on Lump Sum Contract as follows: In case during the implementation of the project, there is one unexecuted item, is the owner in position to say to the contractor that we reserve the right to negotiate it with another item?

0 replies