I am a contractor and once in a while, I get a preliminary notice from my subcontractors which is fine but I have a question: Is it possible to not include the price of the contract in the preliminary notice?

Managing Partner Gibbs Giden LLP

The subcontractor must include the estimated value of the labor and materials that the subcontractor will furnish to the project. Often, that estimated value, of course, comes from you.

Disclaimer: NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. This posting does not create any attorney-client relationship and is neither intended to constitute an advertisement nor a solicitation.
Your answer or comment:
Are you a Registered Expert?
You are not logged in and will be posting
anonymously. Log in Now