I am a contractor and once in a while, I get a preliminary notice from my subcontractors which is fine but I have a question: Is it possible to not include the price of the contract in the preliminary notice?
1 reply
Sep 7, 2019
The subcontractor must include the estimated value of the labor and materials that the subcontractor will furnish to the project. Often, that estimated value, of course, comes from you.