GeorgiaPrompt Payment
Anonymous Contractor

Hi. If you are a contractor who is late fulfilling a contract and you are asked to stop mid-project due to this, are you due any monies for the work already done or materials purchased for the project at hand?

2 replies

Partner at Arkin.Law
| 0 reviews
Jul 21, 2021
The short answer is YES.
0 people found this helpful
Helpful
Attorney and Owner at The Storrs Law Firm
| 96 reviews
Jul 21, 2021
Typically, you would be entitled to payment for your performance to the date of suspension/termination. The other party might have a claim for delay costs depending on the facts involved. More facts are needed to analyze your situation; also, your rights will probably be affected by the language in your agreement. If you need further information or have questions, feel free to contact me at (404) 500-6302.
This forum is not a secure form of communication. Use of this forum to contact Richard J. Storrs or the Storrs Law Firm does not create an attorney-client
relationship. No attorney client relationship exists with Richard J. Storrs or the Storrs Law Firm in the absence of a signed engagement letter. By uSee More...
See More...
0 people found this helpful
Helpful