Menu
Home>Levelset Community>Legal Help>My mother is about to remodel her kitchen and bathrooms. Total cost is $47,000.00. What should she expect her payment schedule to be?

My mother is about to remodel her kitchen and bathrooms. Total cost is $47,000.00. What should she expect her payment schedule to be?

NevadaConstruction Contract

She is 92 years old and would like some guidance on what to expect.

1 reply

Aug 5, 2019
That's a great question, and I'm glad you're doing the legwork beforehand to make sure no issues arise later on. Before diving in, the Nevada State Contractors Board has an excellent resource for consumers: A Consumer Overview of Contractors and Contracts

Anyway, it does not appear that Nevada strictly regulates down payments or progress payments on home improvement contracts. Rather, consumers and contractors are left to contract in a way that makes sense to the parties involved. As a general rule of thumb, most construction projects have some startup costs and may require a down payment - but down payments that exceed 10% of the project cost should be viewed with a lot of skepticism. And, any progress payments made after that will likely depend on the amounts paid upfront. The exact schedule for payments can vary a bit from project to project, but I'll lay out some guiding principles below.

Following a down payment, if used, progress payments should generally be tied to the project's progress - not an arbitrary schedule. Payments are generally made when certain milestones are met (based on a certain percentage of completion or when a certain part of the project has been completed). By making periodic progress payments, and by making sure those payments directly relate to the work that's been or is being performed, it's easier to make sure that a contractor hasn't been paid more than what they're currently owed and to be sure that unnecessary risks aren't being taken on.

To determine a payment schedule, it's probably a good idea to sit down with the contractor and discuss the project schedule and what costs are associated with each part of the work. If they're a licensed and reputable contractor (you can do a license search here, and if the payment schedule makes logical sense to the owner (keeping in mind project milestones and the costs associated with each part of the work), then it will be easier to trust that the payment schedule is proper.

Finally, while not a schedule topic, per se - note that it's a good idea to require lien waivers with any disbursements. A lien waiver acts a lot like a receipt. It essentially states that payment has been made for work performed, and it prevents a contractor from using tools like a mechanics lien to try and collect additional payment for work that's been paid for. More on that at the following resources: (1) The Property Owner’s Guide to Lien Waivers; and (2)Nevada Lien Waivers Guide and FAQs. I hope this information was helpful! While there's no one answer to what a payment schedule should look like, I think the above information should be valuable. Here are some additional resources that may help, too:
(1) Nevada Home Improvement Bill of Rights
(2) What You Should Know Before Hiring a Contractor
0 people found this helpful
Helpful