mechanics lien filed but 60 days passed

FloridaLien Deadlines

what to do is suit wasnt filed in the 60 day frame and they disputed the lien

2 replies

Dec 4, 2020

If you filed a lien, they served a notice of contest of lien, and you did not file suit within the 60 days, your lien is lost. You did not say who your contract is with, but you are left with bringing a breach of contract lawsuit against your customer - whether that's the owner, the GC or a subcontractor.

0 people found this helpful
Helpful
Dec 5, 2020

You likely still have contractual claims, but no lien claim. You should contact a construction attorney to see what your rights are. 