Lien Rights Timeline

GeorgiaLien Deadlines
David Lee

We're coming up on 90 days since last doing work on a project. The owner, who we couldn't get onsite to punch the project, just visited the site this week & is requesting punch work to be completed. Will that extend our lien deadline by another 90 days. He owes us $52k.

1 reply

Attorney and Owner at The Storrs Law Firm
| 96 reviews
Mar 24, 2023

It's not a hard and fast issue, but generally punch list work does qualify to extend the window to file a lien. It must be original scope work and not warranty items.