Lien a Private Project

CaliforniaSlow Payment

We are currently working on a job with a Subcontractor, who is contracted with a General Contractor. We are acting as a Sub-Subcontractor for this project. We have not completed work on the project. The project is private. The Subcontractor is 78 days past due on a billing to us. Can we file a lien on the project even though we're still activity working on the project? I'm getting mixed information on the Levelset website FAQ.

1 reply

Jan 1, 2023

Under Civil Code 8414, you have to be done providing work. You need a preliminary lien before that though.