I have a customer who is past due . We still show we have product to provide for the project however, since the customer is past due on payment on this project , we are not giving any more product, until he pays. I guess during this time the customer could go somewhere else and buy. Do I leave the last product provided open or do I go ahead and list the date as of right now that has been the last date provided, even though there is more product, he just cannot get it right now. My lien date is coming up asap if i have to put the last date as of right now. This is a project in SC so any help would be greatly appreciated. thanks

3 replies

The critical date is the last day you supplied material to the project. Material that is earmarked for the Project but hasn't actually been supplied is not included in a mechanic's lien. The deadline to record and serve the lien is 90 days from the last date of supply of material. Please reach out if you have further questions.

This does not create an attorney-client relationship between you and Paul Rahn or the firm of Robertston Hollingsworth Manos & Rahn. Paul Rahn does not
accept new clients without a written engagement agreement and conflicts check. Answers should not be taken as legal advice as the full set of facSee More...
See More...
0 people found this helpful
Helpful
Carole teague
Agent at The Systems Depot
Jan 30, 2023

Thank you!

0
Report Spam
Feb 11, 2023

Call or email to remind students of this delay. When I'm playing https://basketballstars2.com
and I get slow, I get annoyed.

0
Report Spam