Hi I see the notice of intent to file a lien was delivered on Jan 19th , do I have 10 days to file a lien ? meaning I can request to file the lien in here by 29th?
A Notice of Intent to Lien isn't an actual requirement in the mechanics lien process in Washington, its an optional notice that can typically induce payment without having to actually file a claim. Thus, the lien deadline is not calculated from that date. Rather, a WA mechanics lien deadline is 90 days measured from the last date of furnishing labor and/or materials to the project.