is there a time limits that a 20 day preliminary notice can stand on a property

California

Work was started in June 2021. Work completed August 12021. Awaiting final payment on this job.

1 reply

Dec 10, 2021
If the work was completed in August 1, 2021, you have at most ninety days in which to record a mechanics lien (assuming this is for a private works project). I suggest you consult with an attorney who is knowledgeable about construction claims to advise you as to what rights you have at this point in time.