I would like to know if there is a deadline for filing a lien in Pennsylvania.
Thanks you!
1 reply
Apr 19, 2022
Yes ... You must file a mechanics lien within 6 months of the last day that you performed work on a Project. If you are a subcontractor, you will also need to send out of Notice of Intent to File a Mechanics' Lien Claim to the owner at least 30 days before you file your mechanics' lien claim. That Notice required in order for a subcontractor to file a mechanics ' lien. If you need help preparing the Notice or the Mechanics Lien, please give me a call at (412) 242-4400.