The contractor we work for insists that we the subcontractor add a 10% fee and administration fee for them on our invoicing and scope of work. I feel like this is illegal but I am unsure.
Based on your question, I can't imagine that you would have to do that. This looks like the contractor wants to pad his billing. Generally, a sub would bill the GC with its own markup as part of its pricing and then the GC would add its fee. I can't opine further given the absence of detail, etc.
This forum is not a secure form of communication. Use of this forum to contact The Law Office of Christopher G. Hill, PC or Christopher G. Hill does not create an attorney-client relationship. Please do not send confidential information through the use of this forum. By use of this forum, you acknoSee More...See More...