Florida

last day worked was 07/30/2021...multiple promises to be paid...

2 replies

Oct 7, 2021
Please identify the county where the property is located.
0 people found this helpful
Helpful
Oct 12, 2021

You should do this right away. You have 90 days after your final furnishing of labor, materials or service to record a claim of lien. If you are a sub or supplier, you will need to have served a notice to owner before you can record a claim of lien.

 

Expect to pay about $600-$700 to have a lien prepared and recorded.

 

 

 

 