last day worked was 07/30/2021...multiple promises to be paid...
You should do this right away. You have 90 days after your final furnishing of labor, materials or service to record a claim of lien. If you are a sub or supplier, you will need to have served a notice to owner before you can record a claim of lien.
Expect to pay about $600-$700 to have a lien prepared and recorded.