Menu
Home>Levelset Community>Legal Help>I missed the preliminary notice deadline; can I still file a lien?

I missed the preliminary notice deadline; can I still file a lien?

Georgia
Chris Murphy
CFO at The Whalen Company

I am a material supplier and I missed the preliminary notice deadline. Can I still file a lien if I don't collect my receivable? The equipment for this job has not yet fully shipped. We still owe the customer 3 units, which we are holding as leverage for payment.

1 reply

Partner at Adams and Reese
| 0 reviews
Sep 13, 2022
This depends on whether a Notice of Commencement was filed and/or if the Notice of Commencement is deficient. A search of the GC's name in the GSCCA will provide this information.
0 people found this helpful
Helpful