Menu
Home>Levelset Community>Legal Help>I am a general roofing contractor. There is no lender on the project. Customer is not paying. I am past the Preliminary Lien time period because we understood that we do not have to prelim in this situation. Can we still file a Mechanics Lien

I am a general roofing contractor. There is no lender on the project. Customer is not paying. I am past the Preliminary Lien time period because we understood that we do not have to prelim in this situation. Can we still file a Mechanics Lien

CaliforniaLien DeadlinesMechanics LienPreliminary Notice
Anonymous Contractor

We are the general. Were told do not need to file a pre lien and that date has passed. There is no lender. Can we still file a mechanics lien?

1 reply

Levelset Admin at Levelset
| 1,000 reviews
Jan 4, 2018
Thank you for the question, and I'm sorry to hear about your situation. A contractor who contracted directly with an owner is not required to send preliminary notice where no lender is present. Even where preliminary notice is not a prerequisite for filing a lien, the lien must still be filed within the filing deadline - for a direct contractor, this will be before the earlier of either 90 days after completion of the work of improvement or 60 days after the owner records a Notice of Completion or Cessation. If no preliminary notice was required and the lien filing deadline has not yet passed, lien rights will generally still be available.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...
0 people found this helpful
Helpful