Menu
Home>Levelset Community>Legal Help>how long after the work was performed do we have before we need to start the process?

how long after the work was performed do we have before we need to start the process?

Wisconsin

We're a sub- contractor in Wisconsin looking to potentially file a lien on a residential property due to non payment from the general contractor. The work was already performed on 3/8/23 , how long do we have before we must start the process?

1 reply

Apr 12, 2023
Thank you for reaching out. Check out this Levelset article about Wisconsin lien requirements that may address your question: https://www.levelset.com/mechanics-lien/wisconsin-lien-law-faqs/
0 people found this helpful
Helpful