FloridaPay Applications

If you give an allowance in the contract for material but only use a portion of that allowance Do you then bill out a credit for the difference not used and bill out the rest of the allowance so it cancels out?

1 reply

Jan 26, 2021

If there is an unused portion of an allowance, you should refund that to the customer, or use it as a credit toward the balance owed to you. Alternatively, you should treat the allowance as your contract requires you to.

0 people found this helpful