Menu
Home>Levelset Community>Legal Help>how do I file a lien in Georgia if I'm a subcontractor?

how do I file a lien in Georgia if I'm a subcontractor?

Georgia

i'm a sub and want to file a lien

1 reply

Aug 27, 2021
There are important deadlines to consider with respect to filing your lien. In Georgia, you are required to file a Mechanic's Lien with 90 days of the last day work was performed on the property. There are other subsequent deadlines to consider after this date, but if you miss the first hurdle then you will lose ability to assert a lien against the property. I recommend you work with Levelset or contact an attorney to determine the viability of filing a lien.
1 person found this helpful
Helpful