Menu
Home>Levelset Community>Legal Help>How do I file a delay claim?

How do I file a delay claim?

California

our scope of work (drywall & metal stud framing) has been delayed due to circumstances not in our control. We need example of letter & costs we can use to calculate our claim

1 reply

Apr 8, 2022
The first thing you are going to need to do is look at your contract and determine what the requirements are for making a delay claim and what you are entitled to (additional time, monetary compensation or both). Then you prepare your letter, which will be based on the contractual requirements
1 person found this helpful
Helpful