I filed a mechanics lien in July for non-payment of completed work. Will I need to extend the lien to keep it active in 1 year?

2 replies

Attorney at Kurien Oullette LLC
| 4 reviews
Sep 16, 2022
An action to enforce a Connecticut mechanics lien must be commenced within 1 year after recording lien. Failure to file an action prior to such 1-year period will automatically extinguish the lien. There are no extensions.
0 people found this helpful
Helpful
Attorney, Partner at Michelson, Kane, Royster And Barger PC
| 2 reviews
Sep 19, 2022
There is no way to extend a lien beyond one year in CT. By statute, the lien must be foreclosed within 1 year of recording.