Ultimately I assume your delivered materials and/or equipment were then transported to the project site for application/improvement, correct? If that's the case, your rights aren't negatively impacted. Be sure to file your Preliminary Notice within 30 days from the completion date, then your lien within 90 days from the last day of the completion month. The only way a supplier's lien rights would be negatively impacted is if they're unlicensed, in which case the right to lien is forfeited altogether.
Best of luck!
One other consideration is that, in order to be lienable, the materials must be incorporated into the real estate. In other words, one cannot lien for offsite materials. Once the materials are in fact installed/incorporated, they are subject to lien.
This forum is not a secure form of communication. Use of this forum to contact The Law Office of Christopher G. Hill, PC or Christopher G. Hill does not create an attorney-client relationship. Please do not send confidential information through the use of this forum. By use of this forum, you acknoSee More...See More...