Menu
Home>Levelset Community>Legal Help>Filing a Stop Notice within 90 days of completion, is this 90 days for the whole project or just my portion?

Filing a Stop Notice within 90 days of completion, is this 90 days for the whole project or just my portion?

CaliforniaNotice of CompletionStop Notice
Katie Kovenich
Controller at CRG

I am the subcontractor and was informed by a Levelset representative to file a Stop Notice to initiate a Lien on a project. The representative stated that a Notice of Completion must be filed as well. I did not record the Notice of Completion within 30 days, was informed about the 90 days from actual completion and do not know if the 90 days entitles the whole project or just the portion I worked on.

2 replies

If you are a subcontractor, you would not be filing a notice of completion. You may have lien, stop payment notice, and/or payment bond rights if you served a preliminary notice (if required) and timely serve/record your claims. These deadlines generally run from the date the project has achieved completion.

NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The
content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settSee More...
See More...
1 person found this helpful
Helpful
Katie Kovenich
Controller at CRG
Nov 16, 2022
We know that we have to initiate a Stop Notice. We know that the notice must be within 30 days. Does the 30 days entitle the completion of the Whole project or just our PORTION? Please answer ASAP. Every day we are not able to file a notice we are losing out. I have been trying to settle this for a week now.
0
Report Spam