I'm a General Contractor who has completed a project roughly a year a go in McKinney, TX. There were 2 agreements that were executed for this project: Contract amount on the AIA 101, and a separate Funds Control fee separate from the AIA101. The Contract amount has been paid off after completion, however, a separate Funds Control agreement that was also executed amongst us (GC) and the client hasn't been honored. I was interested in filing a Mechanic's Lien for this case on nonpayment for "Labor" regarding funds management on the project. However, it doesn't necessarily pertain to the contract amount. Would filing the Mechanic's Lien be appropriate for this type of case on nonpayment from client?
Thank you for the information.
Asides from the timespan of the funds control agreement, would this type of case for nonpayment be appropriate to file a Mechanic's Lien?