I'm preparing NOC's to send out to 106 contractors and subs, and want to know how to legally get these notices to them.

3 replies

Principal Attorney and Founder at Arizona Property Law
| 20 reviews
Nov 3, 2021
You will want to review ARS 33-993, which contains the requirements for a notice of completion. An NOC must be recorded with the county recorder and "the person recording the notice, within fifteen days of recording, shall mail by certified or registered mail postage prepaid a copy of the notice of completion and a written statement of the date of recording and the county recorder's record location information to the original contractor and all persons from whom the owner has previously received a preliminary twenty day notice. In the event the owner or its agent fails to mail a copy of the notice of completion and a written statement of the date of recording and the county recorder's record location information within fifteen days of recording to any person from whom the owner has received a preliminary twenty day notice, such person shall have one hundred twenty days from completion as defined in section 33-993 to impress and secure the lien provided for in this article."
1 person found this helpful
Helpful
Anonymous Contractor
Question Author
Nov 3, 2021
Thank you! We've done all the above and just need to get the NOC's mailed out now.
0
Report Spam
Principal Attorney and Founder at Arizona Property Law
| 20 reviews
Nov 3, 2021
Awesome!