Do you file a prelien on design and engineering of a project

CaliforniaLien DeadlinesPreliminary Notice

This is for design and engineering only at this point. Do we file a prelien for this?

2 replies

Oct 26, 2020

Yes, you should serve the direct contractor, owner, and construction with a preliminary notice. A preliminary notice only preserves lien rights for 20 days prior to sending the notice, and for any work done after the notice is sent. 

0 people found this helpful
Helpful
Oct 27, 2020
Yes, you should do a Preliminary Notice for this type of work. It’s best to get into the habit of sending a Preliminary Notice on every job you do. That way it becomes automatic and you won’t forget when it really matters.