i am a subcontractor on a commercial project in Texas and have billed for March and not seen any money.
1 reply
Jul 6, 2020
I see that you tagged the question as a "bond claim" question, but the question itself states the job is commercial. Certainly, notice requirements will depend on the type of project being worked on - so here are two resources that should help you determine the schedule for your monthly notices (if necessary):
- Texas Public Project Monthly Notice Calendar (Bond Claims)- Texas Private Project Monthly Notice Calendar (Mechanics Liens)
Both of those linked calendars should provide a clear timeframe for when notice must be sent. Additionally, keep in mind that monthly notices are based on when the work was performed - not necessarily when the work was billed.
For further discussion on Texas monthly notices: Texas Preliminary Notice Guide and FAQs.