I see that you tagged the question as a "bond claim" question, but the question itself states the job is commercial. Certainly, notice requirements will depend on the type of project being worked on - so here are two resources that should help you determine the schedule for your monthly notices (if necessary):
- Texas Public Project Monthly Notice Calendar (Bond Claims)- Texas Private Project Monthly Notice Calendar (Mechanics Liens)
Both of those linked calendars should provide a clear timeframe for when notice must be sent. Additionally, keep in mind that monthly notices are based on when the work was performed - not necessarily when the work was billed.
For further discussion on Texas monthly notices: Texas Preliminary Notice Guide and FAQs.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...See More...