Do I have to continue sending monthly notices on a project in TX after I file a mechanics lien? This project is specifically an "Owner Occupied Residential" type, and I am the Material Supplier working directly with the Subcontractor.
1 reply
May 11, 2018
That's an interesting question. Monthly notices must be sent in Texas in order to trap funds and preserve the right to file a mechanics lien. Once a mechanics lien has been filed, the preservation of that right (to file a mechanics lien) is no longer necessary since that lien has actually been filed. Conceivably, though, if a claimant continued to perform work after their lien was filed, notice might be required to preserve the lienability of any work performed after the lien filing.
Post a question in our community to get free advice from Construction Attorneys in your state, typically within a week. Questions are public, so do not share personal information. For extra privacy, select the anonymous option.