Menu
Home>Levelset Community>Legal Help>Certificate of Completion -Our contractor added 20% (overhead/profit) to include all costs of subcontractors.

Certificate of Completion -Our contractor added 20% (overhead/profit) to include all costs of subcontractors.

FloridaPayment Disputes

We were surprised by final invoice from contractor which included a markup on subs. He told us the Certificate of Completion had to be revised to include the total cost of the project. The 20% markup was not stated in the original contract. Is this legitimate?

1 reply

Jan 2, 2020
I'm not entirely sure I understand the situation - but, generally, a contractor is only entitled to bill based on the contract they've signed and prices they've agreed to charge. It's common for these amounts to escalate a bit due to change orders issued throughout the life of the job and unexpected additional costs for performing the work. However, if a contractor has agreed to bill based on some formula, they won't be entitled to arbitrarily change that formula when it comes time to bill the job.
0 people found this helpful
Helpful