Can I take partial payment?

South Carolina
Mark Scholz
Owner at Streamline Construction Services, LLC

We filed a lien on a project back in Nov 2022 and the GC wants to make a partial payment on the balance owed. Can I take this or is that putting me at risk to not get paid for the remaining balance?

1 reply

It is hard to say without knowing all of the details which include the terms and conditions of your contract but as long as you aren't signing a lien waiver or satisfaction and the check isn't marked "payment in full" or isn't accompanied by something saying that is all they are paying you there is a good chance you can accept the payment without much risk. Having said that, the devil is in the details and we are happy to discuss the facts of your particular situation if you wish. Just give us a call.  

Regards,

Paul Rahn

This does not create an attorney-client relationship between you and Paul Rahn or the firm of Robertston Hollingsworth Manos & Rahn. Paul Rahn does not
accept new clients without a written engagement agreement and conflicts check. Answers should not be taken as legal advice as the full set of facSee More...