Can I still submit mechanics lien?

UtahPreliminary Notice
Anonymous Contractor

I wasn’t very knowledgeable about the process to file a mechanics lien so I might have submitted the Preliminary Notice late. Can I still do it if it’s only a day over 20 days?

Related Article
How Do You File a Preliminary Notice in Utah?

1 reply

Attorney at Skoubye Nielson & Johansen, Llc
| 5 reviews
Sep 23, 2021

Yes. However, a preliminary notice filed more than 20 days after the commencement of your construction work will only attach to work that is provided 5 days after the preliminary notice is filed. If your work is complete or a notice of completion is filed, the preliminary notice will have no effect. Here is the statute that provides these rules: https://le.utah.gov/xcode/Title38/Chapter1A/38-1a-S501.html.   

No attorney client relationship will be formed with Mr. Thornton or Skoubye Nielsen & Johansen, LLC (snjlegal.com) unless Mr. Thornton is contacted directly
and agrees to enter into an attorney-client relationship through a written agreement. This post is for information purposes only and does not consSee More...
See More...
0 people found this helpful
Helpful