Menu
Home>Levelset Community>Legal Help>Can i File a mechanics lien and send out notices past the deadline

Can i File a mechanics lien and send out notices past the deadline

ColoradoLien DeadlinesMechanics LienPayment DisputesPreliminary Notice
Anonymous Contractor

the sub was advanced the funds and the lender has not been paid, a lien needs to be filed however it seems the deadline for document to be sent has past, can the documents still be sent and lien be filed??

2 replies

Construction Attorney at The Green Law Group
| 13 reviews
Oct 26, 2020

There is not enough information here to evaluate your best options for collections. If you are unsure how to secure your right to payment, I recommend that you consult with a qualified construction attorney to review the facts of your case and provide a recommended course of action. 

Nothing in this answer is intended to create an attorney-client relationship. Answers to questions should not be acted upon as legal advice, but are general in
nature and based on a limited understanding the facts of your situation. The facts of every situation are unique and may have specific legal ramifiSee More...
See More...
0 people found this helpful
Helpful
Construction Attorney at The Green Law Group
| 13 reviews
Oct 27, 2020

I apologize, I have my questions set to California only, bur for whatever reason the LevelSet website sometimes kicks me questions from other states. I am not authorized to practice law in Colorado, and hope you can find the answer to questions.

Nothing in this answer is intended to create an attorney-client relationship. Answers to questions should not be acted upon as legal advice, but are general in
nature and based on a limited understanding the facts of your situation. The facts of every situation are unique and may have specific legal ramifiSee More...
See More...
1 person found this helpful
Helpful