Our Company incorrectly listed on the NTO whom we were hired by as the General contractor and the actual General Contractor was never furnished proper copy of your NTO within the first 45 days of you working on the project. The GC claims we did not remedy the inaccurate NTO until after project completion. Your failure to properly complete the NTO did not give the GC the opportunity to request progress payment waivers from the hiring company to know that we were being paid throughout the project. Is our NTO as filed legal to place a lien if needed in situations like this?
It's probably too late. If the owner has made final payment and the NTO was not corrected within the 45 days work performed or materials delivered. You should be able to sue the GC for breach.