Menu
Home>Levelset Community>Legal Help>Can I file a lien if customer refuse to pay a progress payment

Can I file a lien if customer refuse to pay a progress payment

CaliforniaLien DeadlinesMechanics LienPayment DisputesRecovery Options
Anonymous Contractor

Customer is not following progress payment according to contract, we send a stop notice and she still refuse to pay, can I file a lien based on a progress payment? Project #1986330

1 reply

Levelset Admin at Levelset
| 1,000 reviews
Apr 3, 2018
This is a good question. In most states, even where a claimant will continue to provide work, a lien may be filed. However, in California, a claimant other than a direct contractor may not enforce a lien claim unless it is (a) filed after the claimant ceases to provide work, but (b) filed before either 90 days after completion of the improvement or 30 days after a Notice of Completion/Cessation has been field (whichever comes first).

For direct contractors, the time for filing a lien after the contract is completed, but before either 90 days after completion or 60 days after an owner records a Notice of Completion/Cessation (again- whichever comes first). Of course, this does not necessarily mean that a lien may not be filed for a progress payment owed. For parties other than a direct contractor, it merely means that a claimant must cease to provide work prior to filing a lien.

For direct contractors, the "completion" of the direct contract requirement sticks out- but § 8180(a) of the California mechanics lien statute defines "completion" as (1) actual completion, (2) cessation of labor accompanied by occupation or use by the owner, (3) cessation of labor for a continuous period of 60 days, or (4) recordation of a Notice of Cessation after a continuous cessation of at least 30 days. Thus, if a claimant wishes to file a lien over an unpaid progress payment, their work will have to be ceased prior to filing a mechanics lien.

Granted, there are certainly risks involved in such a work stoppage - a customer may use such an event as an opportunity to bring their own legal claims, such as a breach of contract. Informing a customer that work will be ceased and a lien will be filed if nonpayment continues may be enough in and of itself to convince them to pay what is due. If payment is still not forthcoming, a mechanics lien may be one of many available options for moving forward.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...
0 people found this helpful
Helpful