Can I do a bond claim if I didn't send a preliminary notice of a federal job?

NevadaBond ClaimsMiller Act
Anonymous General Contractor

I was a subcontractor on federal job and we havent been on the job site since Sept last year. Can I still do a Bond claim?

1 reply

If you were a sub-subcontractor (i.e., not in direct privity with the general contractor), you almost certainly would have needed to give a timely Miller Act Bond Claim Notice within 90 days of your last furnishing labor or materials to the project. What constitutes proper notice is a bit of a gray area so you should consult with an experienced construction attorney with experience on federal projects. More information is here https://www.levelset.com/blog/miller-act/

NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The