ArizonaConstruction Contract

The GC is stating we are in breach of contract because the QP of the contractors license passed away and we have not had a new qualifying party assigned but are in the process of doing so. Since the job has not started can we still be in breach of that contract technically?

1 reply

Sep 20, 2021
Arizona law requires that you have qualifying party who holds the license. You don't want to start work without a license because if they don't pay you you may not be able to sue for the amount owed. Depending on where you are in the process of getting a new qualifying party you should keep them updated on your progress and send them any paperwork showing it.
0 people found this helpful