South Carolina Prompt Payment Overview

South Carolina Prompt Payment Requirements


21
DAYS
Prime Contractors

For Prime Contractors, progress payment must be made within 21 days after invoice


7
DAYS
Subcontractors

For Subcontractors, payment due within 7 days after payment received from above


7
DAYS
Suppliers

For Suppliers, payment due within 7 days after payment received from above


1%
/ MONTH
Interest & Fees

Interest at 1% month, only if invoice contains a cite to the relevant statute and a warning that interest may become due.

21
DAYS
Prime Contractors

For Prime (General) Contractors, payment due within 21 days of invoice.


7
DAYS
Subcontractors

For Subcontractors, payment due within 7 days of receipt of payment from above. Can be modified by contract.


7
DAYS
Suppliers

For Suppliers, payment due within 7 days of receipt of payment from above. Can be modified by contract.


1%
/ MONTH
Interest & Fees

Interest at 1% month, only if invoice contains a cite to the relevant statute and a warning that interest may become due.

Prompt payment laws are a set of rules that regulate the acceptable amount of time in which payments must be made to contractors and subs. This is to ensure that everyone on a construction project is paid in a timely fashion. These statutes provide a framework for the timing of payments to ensure cash flow and working capital.

Projects Covered by Prompt Payment in South Carolina

South Carolina has one Prompt Payment Act that covers both public and private construction projects, found in S.C. Code §29-6-10. There are only three exceptions: (1) residential home-building projects, (2) improvements to residential projects with 16 or fewer units, or (3) when the improvements aren’t financed by the owner. In every other circumstance, these provisions will apply.

Payment Deadlines

When a direct contractor submits a request for payment after performing in accordance with the contract terms, the owner or public entity must release payment within 21 days of receipt of the pay request. Once the contractor has received payment, they must pay their subs and suppliers within 7 days of receipt of funds; and so on down the payment chain.

Penalties for Late Payment

The statute does provide legitimate grounds for a paying party to withhold payment. This includes things such as unsatisfactory job progress, disputed or defective work, third-party claims, and failure to make timely payments. If payment is wrongfully withheld (for any other reason than one of the few provided), the unpaid balance will be subject to interest.

The rate of interest that will accrue is 1% per month. However, parties will not be entitled to interest accrual if notice of the prompt pay statute isn’t provided at the time payment is requested. Best practice? Include the language on every invoice or pay application.

Attorney fees may also be available, depending on the circumstances. If a “due and just” demand for payment is sent by certified or registered mail, the party receiving the claim must make a reasonable and fair investigation of the merits of the claim. If the person fails to conduct a fair investigation, or they unreasonably refuse to pay the claim, they will be liable for attorney’s fees.

South Carolina Prompt Payment Frequently Asked Questions

South Carolina Prompt Payment Private Projects FAQs

Do I have to send a letter or file anything to qualify for Prompt Payment Penalties or Remedies in South Carolina?

In order for the provisions of the South Carolina prompt pay statutes to apply, the party requesting payment must be entitled to payment pursuant to the terms of the contract, and must submit a pay request based on the labor and/or materials furnished.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include Prompt Payment Fees in my South Carolina Mechanics Liens Claim or Bond Claim?

No. South Carolina doesn’t allow miscellaneous amounts to be included on the face of a mechanics lien.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Prompt Payment Statutes, can I obtain interest or other Penalty Payments?

In order for interest to accrue on late payments in South Carolina, the party against whom the interest will accrue must be notified of the statutory provisions (and their content) at the time the request for payment is made.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

South Carolina allows payments to be withheld for the following reasons:

  1. Unsatisfactory progress;
  2. Defective and un-remedied work;
  3. Disputed work;
  4. Filed or reasonably expected third-party claims;
  5. Failure to pay down-the-chain;
  6. Reasonable evidence that the contract cannot be completed for the balance due.
Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What is the best practice for making a demand to a non-paying party to get Prompt Payment Fees?

Sending a notice of intent to lien and prompt payment demand is generally the best method for encouraging parties to make payment.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

South Carolina Prompt Payment Public Projects FAQs

Do I have to send a letter or file anything to qualify for Prompt Payment Penalties or Remedies in South Carolina?

In order for the provisions of the South Carolina prompt pay statutes to apply, the party requesting payment must be entitled to payment pursuant to the terms of the contract, and must submit a pay request based on the labor and/or materials furnished.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include Prompt Payment Fees in my South Carolina Mechanics Liens Claim or Bond Claim?

No. South Carolina doesn’t allow miscellaneous amounts to be included on the face of a bond claim.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Prompt Payment Statutes, can I obtain interest or other Penalty Payments?

In order for interest to accrue on late payments in South Carolina, the party against whom the interest will accrue must be notified of the statutory provisions (and their content) at the time the request for payment is made.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

South Carolina allows payments to be withheld for the following reasons:

Unsatisfactory progress;
Defective and un-remedied work;
Disputed work;
Filed or reasonably expected third-party claims;
Failure to pay down-the-chain;
Reasonable evidence that the contract can not be completed for the balance due.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Need More Help with South Carolina Prompt Payment? We're Here.

Ask an expert for free

Check out our payment experts
Construction attorneys: Courtney Stricklen, Christopher Ng, Andrea Goldman, and Peter Ryan

South Carolina Prompt Payment
Recent Questions & Answers

Can I collect interest on the money owed me for over a year?

I have filed a Mechanics Lien on a property in Mt. Pleasant, SC. The home is under contract and am about to be paid the $5300 that has been owed to me for over a year. Am I able to charge them interest on the $5300.00?

How to file a lien in South Carolina

Need to file a South Carolina mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset’s free information.
Step 2
Download your South Carolina Mechanics Lien Form
Step 3 Find your South Carolina County Recorder
See all South Carolina Counties
File with the Mechanics Lien Experts
Product screenshot suggesting a found material supplier on a project details screen.
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

Want to Learn More about How South Carolina Contractors Pay?
Graham-Hodge Associates Inc.
Rating 5.0
D.R. Horton
Rating 5.0
SteelFab Inc
Rating 5.0
Core & Main
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

South Carolina Prompt Payment Statutes

Getting informed about prompt payment laws is important. An examination of South Carolina’s prompt payment laws, the rules and regulations related to payment timing, is important to know your rights and responsibilities as a party on a construction project. Out Carolina’s specific laws can be found in: S.C. Code §§ 29-6-10 et seq., and are reproduced below.

Prompt Payment Statute on Private Projects

§ 29-6-10: Definitions

Unless the context otherwise requires in this chapter:

(1) “Contractor” means a person who contracts with an owner to improve real property or perform construction services for an owner.

(2) “Improve” means to build, effect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property, or to excavate, clear, grade, fill, or landscape any real property, or to construct driveways and roadways, or to furnish materials, including trees and shrubbery, for any of these purposes, or to perform any labor upon these improvements, and also means and includes any design or other professional or skilled services furnished by architects, engineers, land surveyors, and landscape architects.

(3) “Improvement” means all or any part of any building, structure, erection, alteration, demolition, excavation, clearing, grading, filling, or landscaping, including trees and shrubbery, driveways, and roadways on real property.

(4) “Owner” means a person who has an interest in the real property improved and for whom an improvement is made and who ordered the improvement to be made. “Owner” includes any state, local, or municipal government agencies, instrumentalities, or entities.

(5) “Real property” means the real estate that is improved, including lands, leaseholds, tenements, and hereditaments, and improvements placed on the real property.

(6) “Subcontractor” means any person who has contracted to furnish labor or materials to, or has performed labor or supplied materials for, a contractor or another subcontractor in connection with a contract to improve real property.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-20: Right of contractor and subcontractor to payment

Performance by a contractor or subcontractor in accordance with the provisions of his contract entitles him to payment from the party with whom he contracts.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-30: Time and manner of making payment to contractors and subcontractors

When a contractor or a subcontractor has performed in accordance with the provisions of his contract, the owner shall pay the contractor by mailing via first class mail or delivering the undisputed amount of any pay request within twenty-one days of receipt by the owner of any pay request based upon work completed or service provided under the contract, and the contractor shall pay to his subcontractor and each subcontractor shall pay to his subcontractor, within seven days of receipt by the contractor or subcontractor of each periodic or final payment, by mailing via first class mail or delivering the full amount received for that subcontractor’s work and materials based on work completed or service provided under the subcontract.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-40: Grounds on which owner, contractor, or subcontractor may withhold application and certification for payment; contract terms unaffected

Nothing in this chapter prevents the owner, the contractor, or a subcontractor from withholding application and certification for payment because of the following: unsatisfactory job progress, defective construction not remedied, disputed work, third party claims filed or reasonable evidence that claim will be filed, failure of contractor or subcontractor to make timely payments for labor, equipment, and materials, damage to owner, contractor, or another subcontractor, reasonable evidence that contract or subcontract cannot be completed for the unpaid balance of the contract or subcontract sum, or a reasonable amount for retainage.

Nothing in this chapter requires that payments due a contractor from an owner be paid any more frequently than as set forth in the construction documents, nor shall anything in this chapter affect the terms of any agreement between the owner and any lender.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-50: Interest on late payments; specific waiver of requirements of sections 29-6-30 and 29-6-50

If a periodic or final payment to a contractor is delayed by more than twenty-one days or if a periodic or final payment to a subcontractor is delayed by more than seven days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor shall pay his contractor or subcontractor interest, beginning on the due date, at the rate of one percent a month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provisions of this section at the time request for payment is made. Nothing in this chapter shall prohibit owners, contractors, and subcontractors, on private construction projects only, from agreeing by contract to rates of interest and payment periods different from those stipulated in this section, and in this event, these contractual provisions shall control, provided the requirements of Section 29-6-30 and this section are specifically waived, by section number, in conspicuous bold-faced or underlined type. In case of a wilful breach of the contract provisions as to time of payment, the interest rate specified in this section shall apply.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-60: Application of Chapter

The provisions of this chapter do not apply to:

(1) residential homebuilders;

(2) improvements to real property intended for residential purposes which consist of sixteen or fewer residential units; or

(3) private persons or entities owning improvements to real property when the specific improvements are not financed by a nonowner

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-210: Citation of Article

This article may be cited as the “Subcontractors’ and Suppliers’ Payment Protection Act”.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-230: Subcontractor's right to payment from party with whom it contracts

Notwithstanding any other provision of law, performance by a construction subcontractor in accordance with the provisions of its contract entitles the subcontractor to payment from the party with whom it contracts. The payment by the owner to the contractor or the payment by the contractor to another subcontractor or supplier is not, in either case, a condition precedent for payment to the construction subcontractor. Any agreement to the contrary is not enforceable.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-250: Labor and material payment bond; "governmental body" defined

1) When a governmental body is a party to a contract to improve real property, and the contract is for a sum in excess of fifty thousand dollars, the owner of the property shall require the contractor to provide a labor and material payment bond in the full amount of the contract. The bond must be secured by cash or must be issued by a surety company licensed in the State with an “A” minimum rating of performance as stated in the most current publication of “Best Key Rating Guide, Property Liability”. The governmental body may not exact that the labor and material payment bond be furnished by a particular surety company or through a particular agent or broker.

(2) If the contract is for less than one hundred thousand dollars, the governmental body may permit the use of a “B+” rated bond if it justifies that use in writing.

(3) For the purposes of any contract covered by the provisions of this section, it is the duty of the entity contracting for the improvement to take reasonable steps to assure that the appropriate payment bond is issued and is in proper form.

(4) For purposes of this section, “governmental body” means a state government department, commission, council, board, bureau, committee, institution, college, university, technical school, agency, government corporation, or other establishment or official of the executive or judicial branch, and all local political subdivisions. Governmental body excludes the General Assembly or its respective branches or its committees, Legislative Council, the Legislative Services Agency, or any entity created by act of the General Assembly for the purpose of erecting monuments or memorials or commissioning art that is procured exclusively by private funds.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-270: Credit rating of state in which surety company licensed

For any contract for the improvement of real property not covered by the provisions of Section 29-6-250, where a payment bond is required by the contract or otherwise, the bond may only be issued by a surety company licensed in the State with a “B+” minimum rating as stated in the most current publication of “Best Key Rating Guide, Property Liability”.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-290: Contract provisions not to derogate rights of contractor against payment bond

A provision in a contract for the improvement of real property in the State must not operate to derogate the rights of a construction contractor, subcontractor, supplier, or other proper claimant against a payment bond or other form of payment security or protection established by law.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Prompt Payment Statute on Public Projects

§ 29-6-10: Definitions

Unless the context otherwise requires in this chapter:

(1) “Contractor” means a person who contracts with an owner to improve real property or perform construction services for an owner.

(2) “Improve” means to build, effect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property, or to excavate, clear, grade, fill, or landscape any real property, or to construct driveways and roadways, or to furnish materials, including trees and shrubbery, for any of these purposes, or to perform any labor upon these improvements, and also means and includes any design or other professional or skilled services furnished by architects, engineers, land surveyors, and landscape architects.

(3) “Improvement” means all or any part of any building, structure, erection, alteration, demolition, excavation, clearing, grading, filling, or landscaping, including trees and shrubbery, driveways, and roadways on real property.

(4) “Owner” means a person who has an interest in the real property improved and for whom an improvement is made and who ordered the improvement to be made. “Owner” includes any state, local, or municipal government agencies, instrumentalities, or entities.

(5) “Real property” means the real estate that is improved, including lands, leaseholds, tenements, and hereditaments, and improvements placed on the real property.

(6) “Subcontractor” means any person who has contracted to furnish labor or materials to, or has performed labor or supplied materials for, a contractor or another subcontractor in connection with a contract to improve real property.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-20: Right of contractor and subcontractor to payment

Performance by a contractor or subcontractor in accordance with the provisions of his contract entitles him to payment from the party with whom he contracts.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-30: Time and manner of making payment to contractors and subcontractors

When a contractor or a subcontractor has performed in accordance with the provisions of his contract, the owner shall pay the contractor by mailing via first class mail or delivering the undisputed amount of any pay request within twenty-one days of receipt by the owner of any pay request based upon work completed or service provided under the contract, and the contractor shall pay to his subcontractor and each subcontractor shall pay to his subcontractor, within seven days of receipt by the contractor or subcontractor of each periodic or final payment, by mailing via first class mail or delivering the full amount received for that subcontractor’s work and materials based on work completed or service provided under the subcontract.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-40: Grounds on which owner, contractor, or subcontractor may withhold application and certification for payment; contract terms unaffected

Nothing in this chapter prevents the owner, the contractor, or a subcontractor from withholding application and certification for payment because of the following: unsatisfactory job progress, defective construction not remedied, disputed work, third party claims filed or reasonable evidence that claim will be filed, failure of contractor or subcontractor to make timely payments for labor, equipment, and materials, damage to owner, contractor, or another subcontractor, reasonable evidence that contract or subcontract cannot be completed for the unpaid balance of the contract or subcontract sum, or a reasonable amount for retainage.

Nothing in this chapter requires that payments due a contractor from an owner be paid any more frequently than as set forth in the construction documents, nor shall anything in this chapter affect the terms of any agreement between the owner and any lender.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-50: Interest on late payments; specific waiver of requirements of sections 29-6-30 and 29-6-50

If a periodic or final payment to a contractor is delayed by more than twenty-one days or if a periodic or final payment to a subcontractor is delayed by more than seven days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor shall pay his contractor or subcontractor interest, beginning on the due date, at the rate of one percent a month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provisions of this section at the time request for payment is made. Nothing in this chapter shall prohibit owners, contractors, and subcontractors, on private construction projects only, from agreeing by contract to rates of interest and payment periods different from those stipulated in this section, and in this event, these contractual provisions shall control, provided the requirements of Section 29-6-30 and this section are specifically waived, by section number, in conspicuous bold-faced or underlined type. In case of a wilful breach of the contract provisions as to time of payment, the interest rate specified in this section shall apply.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-60: Application of Chapter

The provisions of this chapter do not apply to:

(1) residential homebuilders;

(2) improvements to real property intended for residential purposes which consist of sixteen or fewer residential units; or

(3) private persons or entities owning improvements to real property when the specific improvements are not financed by a nonowner.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-210: Citation of Article

This article may be cited as the “Subcontractors’ and Suppliers’ Payment Protection Act”.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-230: Subcontractor's right to payment from party with whom it contracts

Notwithstanding any other provision of law, performance by a construction subcontractor in accordance with the provisions of its contract entitles the subcontractor to payment from the party with whom it contracts. The payment by the owner to the contractor or the payment by the contractor to another subcontractor or supplier is not, in either case, a condition precedent for payment to the construction subcontractor. Any agreement to the contrary is not enforceable.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-250: Labor and material payment bond; "governmental body" defined

1) When a governmental body is a party to a contract to improve real property, and the contract is for a sum in excess of fifty thousand dollars, the owner of the property shall require the contractor to provide a labor and material payment bond in the full amount of the contract. The bond must be secured by cash or must be issued by a surety company licensed in the State with an “A” minimum rating of performance as stated in the most current publication of “Best Key Rating Guide, Property Liability”. The governmental body may not exact that the labor and material payment bond be furnished by a particular surety company or through a particular agent or broker.

(2) If the contract is for less than one hundred thousand dollars, the governmental body may permit the use of a “B+” rated bond if it justifies that use in writing.

(3) For the purposes of any contract covered by the provisions of this section, it is the duty of the entity contracting for the improvement to take reasonable steps to assure that the appropriate payment bond is issued and is in proper form.

(4) For purposes of this section, “governmental body” means a state government department, commission, council, board, bureau, committee, institution, college, university, technical school, agency, government corporation, or other establishment or official of the executive or judicial branch, and all local political subdivisions. Governmental body excludes the General Assembly or its respective branches or its committees, Legislative Council, the Legislative Services Agency, or any entity created by act of the General Assembly for the purpose of erecting monuments or memorials or commissioning art that is procured exclusively by private funds.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-270: Credit rating of state in which surety company licensed

For any contract for the improvement of real property not covered by the provisions of Section 29-6-250, where a payment bond is required by the contract or otherwise, the bond may only be issued by a surety company licensed in the State with a “B+” minimum rating as stated in the most current publication of “Best Key Rating Guide, Property Liability”.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 29-6-290: Contract provisions not to derogate rights of contractor against payment bond

A provision in a contract for the improvement of real property in the State must not operate to derogate the rights of a construction contractor, subcontractor, supplier, or other proper claimant against a payment bond or other form of payment security or protection established by law.

Summary
South Carolina Prompt Payment Law
Article Name
South Carolina Prompt Payment Law
Description
Summary of South Carolina Prompt Payment requirements and laws for South Carolina construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Trusted by Thousands of South Carolina Contractors Like You
For Help With Prompt Payment