Oregon Prompt Payment Guide and FAQs

Ready? Build Your Free Oregon
Prompt Payment Now

Make Your Prompt Payment Demand Now
Oregon-Prompt-Payment-FAQ

Oregon Prompt Payment Overview

Oregon Prompt Payment Requirements


14
DAYS
Prime Contractors

For Prime Contractors, progress payment must be made within 14 days of invoice. Final payment due within 7 days of completion and approval of project.


7
DAYS
Subcontractors

For Subcontractors, payment due within 7 days after receipt of payment from above.


7
DAYS
Suppliers

For Suppliers, payment due within 7 days after receipt of payment from above.


1.5%
/ MONTH
Interest & Fees

Interest at 1.5% month. Attorney fees to be awarded to prevailing party.

30
DAYS
Prime Contractors

For Prime (General) Contractors, progress payments due within 30 days of invoice; Final payment due within 30 days of final acceptance.


10
DAYS
Subcontractors

For Subcontractors, payments due within 10 days of payment received from above.


10
DAYS
Suppliers

For Suppliers, payments due within 10 days of payment received from above.


DEPENDS
Interest & Fees

Progress payments to primes- statutory rate; Final payments to primes- 1.5% per month; Payments to subs/suppliers- 0.75% per month <br /> Interest at statutory rate. Penalty of 1% month. Attorney fees may be awarded to "substantially" prevailing party.

Prompt payment laws are a set of rules that regulate the acceptable amount of time in which payments must be made to contractors and subs. This is to ensure that everyone on a construction project is paid in a timely fashion. These statutes provide a framework for the timing of payments to ensure cash flow and working capital.

Projects Covered by Prompt Payment in Oregon

The Oregon prompt payment provisions are split into two sections, covering both private and public projects. These statutes govern the timing of all payments on construction projects, and impose penalties for late payment in the form of interest.

Private Projects

Oregon’s prompt payment laws that regulate payments on private construction projects within the state can be found in the Or. Rev. Stat. §720.620 et seq. This applies to all private projects except contracts for construction of low-rise residential dwellings or low-income housing projects.

Deadlines for Payment on Private Projects

Progress payments to the prime contractor from the property owner are due within 14 calendar days of receipt of a proper request for payment. As for final payments, the owner must release payment within 7 calendar days of the owner’s acceptance of the work. These deadlines may be extended only if contract documents use the specific statutory language for the “Notice of Extended Payment Provision.” All other payments to subcontractors and suppliers must be made within 7 days of the higher-tiered party’s receipt of payment.

Penalties for Late Payment for Private Projects

Oregon prompt payment laws do provide a list of reasons why payment can be properly withheld. If none of these circumstances exist, and payment is either late or wrongfully withheld, interest will begin accruing at a rate of 1.5% per month, or the rate set forth in the contract; whichever is higher. Also, if the dispute goes to court or arbitration, the prevailing party will be awarded costs and attorney fees.

Public Projects

Payments on public works projects in Oregon are regulated by Or. Rev. Stat. §279C.320, .505, .515, .570, and .580. These rules do not apply to public contracts for emergency work, minor alterations, or ordinary repair of maintenance of public property.

Deadlines for Payment on Public Projects

Progress payments made from the public entity to the prime contractor must be made to the prime contractor within 30 day of receipt of a request for payment. Final payments to the prime are required to be made within 30 days of receipt of final acceptance of the project. If the pay request is defective or in dispute, the agency must notify the contractor within 15 days of receipt. If the invoice is corrected and submitted within 7 days from receiving notice, payment must still be made according to the original 30-day timeframe. As for all payments to subcontractors and suppliers, payment must be released within 10 days of the higher-tiered party’s receipt of payment from above.

Penalties for Late Payment for Public Projects

The Oregon prompt payment statute for public projects, just as for private jobs, provides a list of reasons that payment can be properly withheld. If these reasons aren’t present, and payment is late or wrongfully withheld, the unpaid balance will be subject to interest penalties. The rates vary depending on the type of payment, and to whom payment is being made.

Late progress payments to prime contractors will accrue interest at a yearly rate of “three times the discount rate in effect in the Federal Reserve Bank whose district includes Oregon.” However, the rate of interest cannot exceed 30%. Final payments to prime contractors will be charged with an interest rate of 1.5% per month. And lastly, all late payments to subcontractors and suppliers will have an interest rate of (% per year (0.75%/month) imposed on the unpaid balance.

Oregon Prompt Payment Frequently Asked Questions

Oregon Prompt Payment Private Projects FAQs

What types of private projects are subject to Oregon’s prompt payment laws?

Oregon’s prompt payment laws apply to all private construction projects that are expected to take 60 days or more to complete. There are, however, a few exceptions, such as:

• Projects subject to the Low-Rise Residential Dwelling Code;

• Public works contracts; &

• Housing in which all or part of the dwelling units are reserved for rental to persons having an income equal to or less than 90 percent of the median household income for the area as determined by the Housing and Community Services Dept. 

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When does payment become due under Oregon’s prompt payment laws?

Payments become due according to a monthly billing cycle and when work and/or materials are provided in accordance with the contract terms.

The parties may contract for a longer payment ‎cycle as long as the contract between the parties includes the statutory Notice of Alternative Billing Cycle language provided under §701.625(2).

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline for payment under Oregon’s prompt payment laws?

Owner to prime contractor

Progress payments must be made within 14 days after receipt of an invoice. While final payments from the owner must be made within 7 days after the work is approved by the property owner.

Note: the owner may make arrangements for a longer payment period if the owner provides drawings and specs that expressly state that an extended payment period is allowed and includes the statutory Notice of Extended Payment Provision language provided under §701.625(3)(b)(B).

Contractors to subs

All other payments down the contracting chain must be made within 7 days of receipt of payment by the higher-tiered party.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

Yes, payments in Oregon may be withheld past the general deadline for the following reasons:

• Unsatisfactory work progress;

• Defective construction work, materials, or products not remedied;

• Disputed work, materials or products, except that the declined amount may not exceed 150 percent of the amount in dispute;

• Failure to comply with other material provisions of the construction contract;

• A third party claim being filed or reasonable evidence that a third party claim will be filed;

• Failure of the original contractor or subcontractor to make timely payments to the subcontractors and materials suppliers;

• Damage to the owner;

• Reasonable evidence that the construction contract cannot be completed for the unpaid balance of the construction contract sum; or

• Other items as allowed under the construction contract terms and conditions.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Oregon’s prompt payment laws, can I obtain interest or other penalty payments?

Yes, all late payments are subject to an interest penalty at a rate of 1.5% per month (or a fraction of a month) until payment is made. However, the parties may agree to a higher interest rate.

Furthermore, in an action to collect interest, the prevailing party will be awarded costs and reasonable attorney fees.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include prompt payment fees in an Oregon mechanics lien claim?

No, it is best practice to limit the amount claimed in an Oregon mechanics lien to the amount unpaid under the contract.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What is the best practice for making a demand to a non-paying party to get prompt payment fees?

Sending a Notice of Intent to Lien along with a Prompt Payment Demand Letter is generally the best method for encouraging parties to make payment. If payment still isn’t forthcoming, a lawsuit may be necessary.

• For more on this, see: How to Make a Claim under Prompt Payment Laws.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Oregon Prompt Payment Public Projects FAQs

What types of public projects are subject to Oregon’s prompt payment laws?

Oregon’s public prompt payment laws apply to all Oregon public improvement contracts except for contracts for emergency work, minor alterations, or ordinary repair or maintenance necessary to preserve a public improvement.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When does payment become due under Oregon’s prompt payment laws?

Payment becomes due when the party performs in accordance with the contract and after the submission of a proper invoice or submitted pursuant to the requirements under the contract.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline for payment under Oregon’s prompt payment laws?

Owner to prime contractors

A contracting agency must pay contractors monthly progress payments (every 30 days) based on the estimates of work approved by the contracting agency

Contractors to subs/suppliers

A prime contractor must pay its subcontractors within ten days after the prime contractor receives payment from the public owner

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

Yes, under the Oregon prompt pay laws, payments may be withheld for the following reasons:

• Unsatisfactory work;

• Disputed work, materials, or products, exceed that the withheld amount may not exceed 150 percent of the amount in dispute;

• Failure to comply with other material provisions of the construction contract;

• A third party claim being filed or reasonable evidence that f third party claim will be filed;

• Failure of the subcontractor to make timely payments to subcontractors and material suppliers for labor, equipment, materials, and products;

• Damage to an original contractor, subcontractor, or material supplier;

• Reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum; or

• Other items as allowed under the subcontract or purchase order terms and conditions.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Oregon’s prompt payment laws, can I obtain interest or other penalty payments?

Late payments from the public entity

An agency must pay penalty interest on any payment not made within the earlier of either:

• 30 days after invoice date; or

• 15 days after the contracting agency approves the payment.

The interest rate is three times the discount rate on 90-day commercial paper in effect at the Federal Reserve Bank in the Federal Reserve district that includes Oregon on the date that is the earlier of either:

• 30 days after the invoice date; or

• 15 days after the contracting agency approves the payment.

The parties may agree to a higher interest rate, however, the agreed-upon interest rate may not exceed 30 percent.

Late payments to subs/suppliers

A prime contractor that does not pay a subcontractor within 30 days after receiving payment from the contracting agency must pay an interest penalty on the amount due. The interest rate is nine percent per year.

The prime contractor must pay the interest from the day after the required payment date to when the amount due is paid.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include prompt payment fees in an Oregon payment bond claim?

No. Oregon doesn’t allow miscellaneous amounts to be included on the face of public payment bond claims.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What is the best practice for making a demand to a non-paying party to get prompt payment fees?

Sending a Notice of Intent to Make a Bond Claim along with a Prompt Payment Demand Letter is generally the best method for encouraging parties to make payment. If payment still isn’t forthcoming, a lawsuit may be necessary.

• For more on this, see: How to Make a Claim under Prompt Payment Laws.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Need More Help with Oregon Prompt Payment? We're Here.

Ask an expert for free

Check out our payment experts
Construction attorneys: Courtney Stricklen, Christopher Ng, Andrea Goldman, and Peter Ryan

Oregon Prompt Payment
Recent Questions & Answers

How to file a lien in Oregon

Need to file a Oregon mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset’s free information.
File with the Mechanics Lien Experts
Product screenshot suggesting a found material supplier on a project details screen.
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

Want to Learn More about How Oregon Contractors Pay?
Truebeck Construction (formerly BNBT Builders)
Rating 5.0
Dallas Glass
Rating 5.0
Culver Glass
Rating 5.0
D.R. Horton
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Oregon Prompt Payment Statutes

Getting informed about prompt payment laws is important. An examination of Oregon’s prompt payment laws, the rules and regulations related to payment timing, is important to know your rights and responsibilities as a party on a construction project. Oregon’s specific laws can be found in Or. Rev. Stat. §§ 701.620 et seq. for private projects, and 279C.320, .505, .515, .570, and .580 for public projects, which are reproduced below. Updated as of November 2021.

Prompt Payment Statute on Private Projects

§ 701.620. Definitions for ORS 701.620 to 701.640

As used in ORS 701.620 to 701.640:

(1) “Construction contract” means a written or oral construction agreement, including all drawings, specifications and addenda relating to:

(a) Excavating, landscaping, demolishing and detaching existing structures, leveling, filling in and other preparation of land for the making and placement of a building, structure or superstructure;

(b) Creation or making of a building, structure or superstructure; and

(c) Alteration, partial construction and repairs done in and upon a building, structure or superstructure.

(2) “Contractor” has the meaning given that term in ORS 87.005.

(3) “Days” means calendar days.

(4) “Material supplier” means any person providing materials or products under a construction contract by oral authorization, written contract, purchase order, price agreement, rental agreement or other contractual means.

(5) “Original contractor” has the meaning given that term in ORS 87.005.

(6) “Owner” has the meaning given that term in ORS 701.410.

(7) “Subcontractor” has the meaning given that term in ORS 87.005.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 701.625. Progress payments; notice requirements; nonapproval of billing or estimate; withholding; final payment

(1) If a construction contract is for construction work that is expected to take 60 or more days to complete, an owner shall make progress payments to the original contractor. By mutual agreement with an original contractor, an owner may make progress payments to the original contractor under a construction contract for which the construction work is expected to take less than 60 days to complete.

(2) The owner shall make progress payments on the basis of a certified billing or estimate for work performed, and for materials or products supplied, during the preceding monthly billing cycle or during an alternative billing cycle identified in the construction contract. If a construction contract identifies an alternative billing cycle, the construction contract must expressly state in a clear and conspicuous manner that there is an alternative billing cycle and the owner must provide on each page of drawings and specifications in the construction contract a statement substantially similar to the following:
______________________________________________________________________________

Notice of Alternative Billing Cycle

The construction contract will allow the owner to require the submission of billings or estimates in billing cycles other than monthly cycles. Billings or estimates for the construction contract shall be submitted as follows:

______________________________________________________________________________

______________________________________________________________________________

______________________________________________________________________________

______________________________________________________________________________

(3)

(a) Except as provided in this subsection, the owner shall:

(A) Make progress payments no later than 14 days after the date the billing is received; and

(B) Make final payment of all remaining amounts no later than seven days after the date that the owner approves the work.

(b) An owner may make progress payments or final payment later than the time allowed under paragraph (a) of this subsection if:

(A) The owner provides drawings and specifications that expressly state in a clear and conspicuous manner that an extended payment period is allowed and identify the extended payment period as a specific number of days after the date that the billing or estimate is received or the date that the owner approves all work; and

(B) The owner provides on each page of drawings and specifications a statement substantially similar to the following:
______________________________________________________________________________

Notice of Extended Payment Provision

The construction contract will allow the owner to make:

(1) Progress payments no later than _____ days after the date a billing or estimate is received.

(2) Final payment of all remaining amounts no later than_____ days after the date the owner approves all work.

______________________________________________________________________________

(4) Payment is not required under this section unless the owner receives from the original contractor a billing or estimate for the work performed or the materials or products supplied in accordance with the terms of the construction contract.

(5) The owner is deemed to have received the billing or estimate when the billing or estimate is received by any person designated by the owner for the receipt, review or approval of the billing or estimate. A billing or estimate is deemed to be certified 10 days after the owner receives the billing or estimate, unless before that time the owner or the owner’s agent prepares and issues a written statement detailing those items in the billing or estimate that are not approved. An owner may decline to approve a billing or estimate or portion of a billing or estimate because of:

(a) Unsatisfactory work progress;

(b) Defective construction work, materials or products not remedied;

(c) Disputed work, materials or products, except that the declined amount may not exceed 150 percent of the amount in dispute;

(d) Failure to comply with other material provisions of the construction contract;

(e) A third party claim being filed or reasonable evidence that a third party claim will be filed;

(f) Failure of the original contractor or a subcontractor to make timely payments to subcontractors and material suppliers for labor, equipment, materials and products;

(g) Damage to the owner;

(h) Reasonable evidence that the construction contract cannot be completed for the unpaid balance of the construction contract sum; or

(i) Other items as allowed under the construction contract terms and conditions.

(6) An owner may extend the period within which the billing or estimate may be certified if:

(a) The owner provides drawings and specifications that expressly allow in a clear and conspicuous manner an extended period within which a billing or estimate may be certified; and

(b) The owner provides for each page of drawings and specifications, including bid drawings and specifications and construction drawings and specifications, a statement substantially similar to the following statement:
______________________________________________________________________________

Notice of Extended Certification Period Provision

The construction contract will allow the owner to certify billings and estimates no later than _____ days after the billings and estimates are received from the original contractor.

______________________________________________________________________________

(7) Any requirement under this section that a statement be provided on a page of drawings or specifications may be satisfied by placing the required statement on either side of the page.

(8) After a subcontractor or material supplier submits a bid or proposal or other written pricing information to an original contractor, an owner and the original contractor may agree in writing to change the specified number of days after certification during which the owner may make payment to the original contractor or within which the owner must certify a billing or estimate. The billings by any subcontractor or material supplier that does not provide written consent to the change remain subject to the certification period indicated in the drawings and specifications. A construction contract may not be changed in a manner that alters the right of any subcontractor or material supplier to receive prompt and timely progress payments as provided under ORS 701.630.

(9) An owner may withhold from a progress payment an amount that is sufficient to pay the direct expenses the owner reasonably expects to incur to correct any items detailed in a written statement under subsection (5) of this section. The owner may also withhold a reasonable amount as retainage. As used in this subsection, “retainage” has the meaning given that term in ORS 701.410.

(10) When an original contractor completes and an owner approves all work under a construction contract, the owner shall make payment in full of all remaining amounts due on the construction contract as described in subsection (3) of this section. When an original contractor completes and an owner approves all work under a portion of a construction contract for which the construction contract states a separate price, the owner shall make payment in full of all remaining amounts due on that portion of the construction contract, subject to the satisfaction of any items detailed under subsection (5) of this section or ORS 701.630(4).

(11) If an owner or a person designated by the owner as responsible for making progress payments on a construction contract does not make a timely payment under this section, the owner shall pay the original contractor interest on the unpaid balance at the rate of one and one-half percent a month or fraction of a month, or at a higher rate as the parties to the construction contract may agree.

(12) On the written request of a subcontractor, the owner shall notify the subcontractor no later than five days after the issuance of a progress payment to the original contractor. On the written request of a subcontractor, the owner shall notify the subcontractor no later than five days after the owner makes the final payment to the original contractor on the construction contract.

(13) If the owner and original contractor are a single entity, that entity shall make progress and final payments to subcontractors and material suppliers as described in subsection (3) or (6) of this section.

(14) In any action, claim or arbitration brought to collect interest pursuant to this section, the prevailing party shall be awarded costs and reasonable attorney fees.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 701.630. Payments to subcontractors and material suppliers; failure to pay; omission of payment

(1) An original contractor, subcontractor or material supplier that performs in accordance with a construction contract is entitled to payment from the party with whom the original contractor, subcontractor or material supplier contracts.

(2)

(a) If a subcontractor has performed in accordance with a construction contract, and the original contractor receives payment from the owner for work performed by the subcontractor, the original contractor shall pay the subcontractor for that work no later than seven days after the original contractor receives the payment. If a material supplier has performed in accordance with a construction contract, and the original contractor receives payment from the owner for materials or products provided by the material supplier, the original contractor shall pay the material supplier for those materials and products no later than seven days after the original contractor receives the payment. An original subcontractor that receives payment under this subsection for work provided to the original subcontractor by another subcontractor, or for materials or products provided to the original subcontractor, shall pay the other subcontractor or material supplier for the work, materials or products no later than seven days after the original subcontractor receives the payment.

(b) Payment is not required under this subsection unless a subcontractor or material supplier provides to the original contractor or subcontractor a billing or invoice for the work performed or materials or products supplied in compliance with the terms of the contract between the parties. Each subcontractor or material supplier must provide an appropriate waiver of any lien for labor, equipment, services, materials or products in accordance with subcontract or purchase order terms and conditions. The original contractor or subcontractor may require that such waivers of lien be notarized.

(3) Any failure to reasonably account for the application or use of payments, as proven in a legal proceeding authorized under the terms of the construction contract, may constitute grounds for disciplinary action by the Construction Contractors Board under ORS 701.098.

(4) An original contractor that submits a billing or estimate to an owner, or an original subcontractor that submits a billing or estimate to the original contractor, may omit from the billing or estimate amounts to be withheld from payment to a subcontractor or material supplier because of:

(a) Unsatisfactory work progress;

(b) Defective construction work, materials or products not remedied;

(c) Disputed work, materials or products, except that the withheld amount may not exceed 150 percent of the amount in dispute;

(d) Failure to comply with other material provisions of the construction contract;

(e) A third party claim being filed or reasonable evidence that a third party claim will be filed;

(f) Failure of the subcontractor to make timely payments to subcontractors and material suppliers for labor, equipment, materials and products;

(g) Damage to an original contractor, subcontractor or material supplier;

(h) Reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum; or

(i) Other items as allowed under the subcontract or purchase order terms and conditions.

(5) An original contractor or original subcontractor may also omit from a billing or estimate a reasonable amount for retainage, except that the amount omitted may not exceed the actual percentage allowed by the construction contract, subcontract or purchase order. As used in this subsection, “retainage” has the meaning given that term in ORS 701.410.

(6) If a progress or final payment to a subcontractor or material supplier is delayed by more than seven days after receipt of a progress or final payment by an original contractor or subcontractor, the original contractor or subcontractor shall pay its subcontractor or material supplier interest beginning on the eighth day, except during periods of time during which payment is withheld pursuant to subsection (4) or (5) of this section, at the rate of one and one-half percent a month or a fraction of a month on the unpaid balance or at such higher rate as the parties agree.

(7) In any action, claim or arbitration brought to collect interest under this section, the prevailing party shall be awarded costs and reasonable attorney fees.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 701.635. Suspension of performance

(1) An original contractor may suspend performance under a construction contract, or if performance is suspended for longer than one month may terminate a construction contract, if the owner fails to make timely payment of the amount certified under ORS 701.625. An original contractor shall provide written notice to an owner at least seven days before the original contractor suspends performance or terminates the construction contract, unless a shorter notice period is prescribed in the construction contract. An original contractor may not be deemed in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection. A construction contract may not extend the notice period under this subsection.

(2) A subcontractor may suspend performance under a construction contract, or if performance is suspended for longer than one month may terminate a construction contract, if the owner fails to make timely payment of amounts certified under ORS 701.625 or the subcontractor does not receive payment for the certified work under ORS 701.630(2). A subcontractor shall provide written notice to the original contractor and owner at least three days before the subcontractor suspends performance or terminates the construction contract, unless a shorter notice period is prescribed in the construction contract. A subcontractor may not be deemed in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection. A construction contract may not extend the notice period under this subsection.

(3) A subcontractor may suspend performance under a construction contract, or if performance is suspended for longer than one month may terminate a construction contract, if the owner makes timely payment of amounts certified under ORS 701.625 for the subcontractor’s work but the original contractor fails to pay the subcontractor for the certified work. A subcontractor shall provide written notice to the original contractor and owner at least seven days before the subcontractor suspends performance or terminates the construction contract, unless a shorter notice period is prescribed in the construction contract. A subcontractor may not be deemed in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection. A construction contract may not extend the notice period under this subsection.

(4) A subcontractor may suspend performance under a construction contract, or if performance is suspended for longer than one month may terminate a construction contract, if the owner declines or fails to approve portions of the contractor’s billing or estimate under ORS 701.625 for that subcontractor’s work and the reasons for nonapproval are not the fault of or directly related to the subcontractor’s work. A subcontractor shall provide written notice to the original contractor and the owner at least seven days before the subcontractor suspends performance or terminates the construction contract, unless a shorter notice period is prescribed in the construction contract. A subcontractor may not be deemed in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection. A construction contract may not extend the notice period under this subsection.

(5) A contractor or subcontractor may not submit a notice of suspension under this section until the lawful period for payment to the contractor or subcontractor has expired.

(6) An original contractor or subcontractor that suspends performance as provided in this section may condition the supplying of further labor, equipment, services, materials or products upon the owner or original contractor paying, in addition to any amounts certified under ORS 701.625, any documented, substantial and reasonably incurred costs for mobilization resulting from the shutdown or start-up of a project.

(7) In any action, claim or arbitration brought pursuant to this section, the prevailing party shall be awarded costs and reasonable attorney fees.

(8) Written notice required under this section is deemed to have been provided if the notice:

(a) Is delivered in person to the owner, original contractor, subcontractor or a person designated by the owner, original contractor or subcontractor to receive notice; or

(b) Is delivered by certified mail, return receipt requested, or other means that provides written, third party verification of delivery to the last business address of the owner, original contractor or subcontractor known to the party giving notice.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 701.640. Prohibition against contrary provisions, covenants or clauses

(1) A construction contract may not include any provision, covenant or clause that:

(a) Makes the construction contract subject to the laws of another state or that requires any litigation, arbitration or other dispute resolution proceeding arising from the construction contract to be conducted in another state; or

(b) States that a party to the construction contract cannot suspend performance under the construction contract or terminate the construction contract if another party to the construction contract fails to make prompt payments under the construction contract pursuant to ORS 701.620 to 701.640.

(2) Any provision, covenant or clause described in subsection (1) of this section is void and unenforceable.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 701.645. Contracts and housing not subject to ORS 701.620 to 701.640

ORS 701.620 to 701.640 do not apply to:

(1) A contract for the construction, alteration, repair, maintenance, moving or demolition of a building that is subject to the Low-Rise Residential Dwelling Code;

(2) A public contract under ORS 279.835 to 279.855 or ORS chapter 279A, 279B or 279C; or

(3) Housing in which all or part of the dwelling units are reserved for rental to persons having an income equal to or less than 80 percent of the median household income for the area as determined by the Housing and Community Services Department.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Prompt Payment Statute on Public Projects

§ 279C.320. Contracts for construction other than public improvements

(1) Contracting agencies shall enter into contracts for emergency work, minor alteration, ordinary repair or maintenance of public improvements, as well as any other construction contract that is not defined as a public improvement under ORS 279A.010, in accordance with the provisions of ORS chapter 279B. Contracts for emergency work are regulated under ORS 279B.080.

(2) Nothing in this section relieves contracting agencies or contractors of any other relevant requirements under this chapter, including payment of prevailing wage rates when applicable.

(3) When construction services are not considered to be a public improvement under this chapter because no funds of a public agency are directly or indirectly used, except for participation that is incidental or related primarily to project design or inspection, the benefiting public body may nonetheless condition acceptance of the services on receipt of such protections as the public body considers to be in the public interest, including a performance bond, a payment bond and appropriate insurance.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 279C.505. Conditions concerning payment, contributions, liens, withholding, drug testing

(1) Every public improvement contract shall contain a condition that the contractor shall:

(a) Make payment promptly, as due, to all persons supplying to the contractor labor or material for the performance of the work provided for in the contract.

(b) Pay all contributions or amounts due the Industrial Accident Fund from the contractor or subcontractor incurred in the performance of the contract.

(c) Not permit any lien or claim to be filed or prosecuted against the state or a county, school district, municipality, municipal corporation or subdivision thereof, on account of any labor or material furnished.

(d) Pay to the Department of Revenue all sums withheld from employees under ORS 316.167.

(2) In addition to the conditions specified in subsection (1) of this section, every public improvement contract shall contain a condition that the contractor shall demonstrate that an employee drug testing program is in place.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 279C.515. Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints

(1) Every public improvement contract must contain a clause or condition that, if the contractor fails, neglects or refuses to pay promptly a person’s claim for labor or services that the person provides to the contractor or a subcontractor in connection with the public improvement contract as the claim becomes due, the proper officer that represents the state or a county, school district, municipality or municipal corporation or a subdivision of the state, county, school district, municipality or municipal corporation may pay the amount of the claim to the person that provides the labor or services and charge the amount of the payment against funds due or to become due the contractor by reason of the contract.

(2) Every public improvement contract must contain a clause or condition that, if the contractor or a first-tier subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract within 30 days after receiving payment from the contracting agency or a contractor, the contractor or first-tier subcontractor owes the person the amount due plus interest charges that begin at the end of the 10-day period within which payment is due under ORS 279C. 580 (4) and that end upon final payment, unless payment is subject to a good faith dispute as defined in ORS 279C. 580. The rate of interest on the amount due is nine percent per annum. The amount of interest may not be waived.

(3) Every public improvement contract and every contract related to the public improvement contract must contain a clause or condition that, if the contractor or a subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract, the person may file a complaint with the Construction Contractors Board, unless payment is subject to a good faith dispute as defined in ORS 279C. 580.

(4) Paying a claim in the manner authorized in this section does not relieve the contractor or the contractor’s surety from obligation with respect to an unpaid claim.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 279C.570. Prompt payment policy; progress payments; retainage; interest; exception; settlement of compensation disputes

(1) It is the policy of the State of Oregon that all payments due on a public improvement contract and owed by a contracting agency shall be paid promptly. No contracting agency is exempt from the provisions of this section.

(2) Contracting agencies shall make progress payments on the contract monthly as work progresses on a public improvement contract. Payments shall be based upon estimates of work completed that are approved by the contracting agency. A progress payment is not considered acceptance or approval of any work or waiver of any defects therein. The contracting agency shall pay to the contractor interest on the progress payment, not including retainage, due the contractor. The interest shall commence 30 days after receipt of the invoice from the contractor or 15 days after the payment is approved by the contracting agency, whichever is the earlier date. The rate of interest charged to the contracting agency on the amount due shall equal three times the discount rate on 90-day commercial paper in effect at the Federal Reserve Bank in the Federal Reserve district that includes Oregon on the date that is 30 days after receipt of the invoice from the contractor or 15 days after the payment is approved by the contracting agency, whichever is the earlier date, but the rate of interest may not exceed 30 percent. If the contract price exceeds $500,000, the contracting agency shall place amounts deducted as retainage into an interest-bearing escrow account. Interest on the retainage amount accrues from the date the payment request is approved until the date the retainage is paid to the contractor to which it is due.

(3) Interest shall be paid automatically when payments become overdue. The contracting agency shall document, calculate and pay any interest due when payment is made on the principal. Interest payments shall accompany payment of net due on public improvement contracts. The contracting agency may not require the contractor to petition, invoice, bill or wait additional days to receive interest due.

(4) When an invoice is filled out incorrectly, when there is any defect or impropriety in any submitted invoice or when there is a good faith dispute, the contracting agency shall so notify the contractor within 15 days stating the reason or reasons the invoice is defective or improper or the reasons for the dispute. A defective or improper invoice, if corrected by the contractor within seven days of being notified by the contracting agency, may not cause a payment to be made later than specified in this section unless interest is also paid.

(5) If requested in writing by a first-tier subcontractor, the contractor, within 10 days after receiving the request, shall send to the first-tier subcontractor a copy of that portion of any invoice, request for payment submitted to the contracting agency or pay document provided by the contracting agency to the contractor specifically related to any labor or materials supplied by the first-tier subcontractor.

(6) Payment of interest may be postponed when payment on the principal is delayed because of disagreement between the contracting agency and the contractor. Whenever a contractor brings formal administrative or judicial action to collect interest due under this section, the prevailing party is entitled to costs and reasonable attorney fees.

(7) A contracting agency may reserve as retainage from any progress payment on a public improvement contract an amount not to exceed five percent of the payment. As work progresses, a contracting agency may reduce the amount of the retainage and the contracting agency may eliminate retainage on any remaining monthly contract payments after 50 percent of the work under the contract is completed if, in the contracting agency’s opinion, such work is progressing satisfactorily. Elimination or reduction of retainage shall be allowed only upon written application by the contractor, and the application shall include written approval of the contractor’s surety. However, when the contract work is 97.5 percent completed the contracting agency may, at the contracting agency’s discretion and without application by the contractor, reduce the retained amount to 100 percent of the value of the contract work remaining to be done. Upon receipt of a written application by the contractor, the contracting agency shall respond in writing within a reasonable time.

(8) The retainage held by a contracting agency shall be included in and paid to the contractor as part of the final payment of the contract price. The contracting agency shall pay to the contractor interest at the rate of 1.5 percent per month on the final payment due the contractor, interest to commence 30 days after the work under the contract has been completed and accepted and to run until the date when the final payment is tendered to the contractor. The contractor shall notify the contracting agency in writing when the contractor considers the work complete and the contracting agency shall, within 15 days after receiving the written notice, either accept the work or notify the contractor of work yet to be performed on the contract. If the contracting agency does not, within the time allowed, notify the contractor of work yet to be performed to fulfill contractual obligations, the interest provided by this subsection shall commence to run 30 days after the end of the 15-day period.

(9)

(a) The contracting agency shall pay, upon settlement or judgment in favor of the contractor regarding any dispute as to the compensation due a contractor for work performed under the terms of a public improvement contract, the amount due plus interest at the rate of two times the discount rate, but not to exceed 30 percent, on 90-day commercial paper in effect at the Federal Reserve Bank in the Federal Reserve district that includes Oregon on the date of the settlement or judgment, and accruing from the later of:

(A) The due date of any progress payment received under the contract for the period in which such work was performed; or

(B) Thirty days after the date on which the claim for the payment under dispute was presented to the contracting agency by the contractor in writing or in accordance with applicable provisions of the contract.

(b) Interest shall be added to and not made a part of the settlement or judgment.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 279C.580. Contractor's relations with subcontractors

(1) A contractor may not request payment from the contracting agency of any amount withheld or retained in accordance with subsection (5) of this section until the contractor has determined and certified to the contracting agency that the subcontractor has determined and certified to the contracting agency that the subcontractor is entitled to the payment.

(2) A dispute between a contractor and first-tier subcontractor relating to the amount or entitlement of a first-tier subcontractor to a payment or a late payment interest penalty under a clause included in the subcontract under subsection (3) or (4) of this section does not constitute a dispute to which the contracting agency is a party. The contracting agency may not be included as a party in any administrative or judicial proceeding involving such a dispute.

(3) Each public improvement contract awarded by a contracting agency must include a clause that requires the contractor to include in each subcontract for property or services the contractor enters into with a first-tier subcontractor, including a material supplier, for the purpose of performing a construction contract:

(a) A payment clause that obligates the contractor to pay the first-tier subcontractor for satisfactory performance under the subcontract within 10 days out of amounts the contracting agency pays to the contractor under the public improvement contract.

(b) A clause that requires the contractor to provide a first-tier subcontractor with a standard form that the first-tier subcontractor may use as an application for payment or as another method by which the subcontractor may claim a payment due from the contractor.

(c) A clause that requires the contractor, except as otherwise provided in this paragraph, to use the same form and regular administrative procedures for processing payments during the entire term of the subcontract. A contractor may change the form or the regular administrative procedures the contractor uses for processing payments if the contractor:

(A) Notifies the subcontractor in writing at least 45 days before the date on which the contractor makes the change; and

(B) Includes with the written notice a copy of the new or changed form or a description of the new or changed procedure.

(d) An interest penalty clause that obligates the contractor, if the contractor does not pay the first-tier subcontractor within 30 days after receiving payment from the contracting agency, to pay the first-tier subcontractor an interest penalty on amounts due in each payment the contractor does not make in accordance with the payment clause included in the subcontract under paragraph (a) of this subsection. A contractor or first-tier subcontractor is not obligated to pay an interest penalty if the only reason that the contractor or first-tier subcontractor did not make payment when payment was due is that the contractor or first-tier subcontractor did not receive payment from the contracting agency or contractor when payment was due. The interest penalty:

(A) Applies to the period that begins on the day after the required payment date and that ends on the date on which the amount due is paid; and

(B) Is computed at the rate specified in ORS 279C. 515 (2).

(4) A public improvement contract that the contracting agency awards shall obligate the contractor, in each of the contractor’s subcontracts, to require the first-tier subcontractor to include a payment clause and an interest penalty clause that conforms to the standards of subsection (3) of this section in each of the first-tier subcontractor’s subcontracts and to require each of the first-tier subcontractor’s subcontractors to include such clauses in the first-tier subcontractors’ subcontracts with each lower-tier subcontractor or supplier.

(5)

(a) The clauses required by subsections (3) and (4) of this section do not impair the right of a contractor or a subcontractor at any tier to negotiate, and to include in the subcontract, provisions that:

(A) Permit the contractor or a subcontractor to retain, in the event of a good faith dispute, an amount not to exceed 150 percent of the amount in dispute from the amount due a subcontractor under the subcontract without incurring any obligation to pay a late payment interest penalty, in accordance with terms and conditions the parties to the subcontract agree upon, giving such recognition as the parties consider appropriate to the ability of a subcontractor to furnish a performance bond and a payment bond;

(B) Permit the contractor or subcontractor to make a determination that part or all of the subcontractor’s request for payment may be withheld in accordance with the subcontract; and

(C) Permit such withholdings without incurring any obligation to pay a late payment interest penalty if:

(i) A notice that conforms to the standards of subsection (8) of this section has been previously furnished to the subcontractor; and

(ii) A copy of any notice a contractor issues under sub-subparagraph (i) of this subparagraph has been furnished to the contracting agency.

(b) As used in this subsection, “good faith dispute” means a documented dispute concerning:

(A) Unsatisfactory job progress.

(B) Defective work not remedied.

(C) Third-party claims filed or reasonable evidence that claims will be filed.

(D) Failure to make timely payments for labor, equipment and materials.

(E) Damage to the contractor or subcontractor.

(F) Reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum.

(6) If, after applying to a contracting agency for payment under a public improvement contract but before paying a subcontractor for the subcontractor’s performance covered by the application, a contractor discovers that all or a portion of the payment otherwise due the subcontractor is subject to withholding from the subcontractor in accordance with the subcontract, the contractor shall:

(a) Furnish to the subcontractor a notice conforming to the standards of subsection (8) of this section as soon as practicable after ascertaining the cause for the withholding, but before the due date for payment to the subcontractor;

(b) Furnish to the contracting agency, as soon as practicable, a copy of the notice furnished to the subcontractor under paragraph (a) of this subsection;

(c) Reduce the progress payment to the subcontractor by an amount not to exceed the amount specified in the notice of withholding furnished under paragraph (a) of this subsection;

(d) Pay the subcontractor as soon as practicable after the correction of the identified subcontract performance deficiency;

(e) Make such payment within:

(A) Seven days after correction of the identified subcontract performance deficiency unless the funds for the payment must be recovered from the contracting agency because of a reduction under paragraph (f)(A) of this subsection; or

(B) Seven days after the contractor recovers the funds from the contracting agency;

(f) Notify the contracting agency upon:

(A) Reduction of the amount of any subsequent certified application for payment; or

(B) Payment to the subcontractor of any withheld amounts of a progress payment, specifying:

(i) The amounts of the progress payments withheld under paragraph (a) of this subsection; and

(ii) The dates on which the withholding began and ended; and

(g) Be obligated to pay to the contracting agency an amount equal to interest on the withheld payments computed in the manner provided in ORS 279C. 570 from the 11th day after receiving the withheld amounts from the contracting agency until:

(A) The day the identified subcontractor performance deficiency is corrected; or

(B) The date that any subsequent payment is reduced under paragraph (f)(A) of this subsection.

(7)

(a) If a contractor, after paying a first-tier subcontractor, receives from a supplier or subcontractor of the first-tier subcontractor a written notice asserting a deficiency in the first-tier subcontractor’s performance under the public improvement contract for which the contractor may be ultimately liable and the contractor determines that all or a portion of future payments otherwise due the first-tier subcontractor is subject to withholding in accordance with the subcontract, the contractor may, without incurring an obligation to pay a late payment interest penalty under subsection (6)(e) of this section:

(A) Furnish to the first-tier subcontractor a notice that conforms to the standards of subsection (8) of this section as soon as practicable after making the determination; and

(B) Withhold from the first-tier subcontractor’s next available progress payment or payments an amount not to exceed the amount specified in the notice of withholding furnished under subparagraph (A) of this paragraph.

(b) As soon as practicable, but not later than 10 days after receiving satisfactory written notice that the identified subcontract performance deficiency has been corrected, the contractor shall pay the amount withheld under paragraph (a)(B) of this subsection to the first-tier subcontractor, or shall incur an obligation to pay a late payment interest penalty to the first-tier subcontractor computed at the rate specified in ORS 279C. 570.

(8) A written notice of any withholding must be issued to a subcontractor, with a copy to the contracting agency, that specifies:

(a) The amount to be withheld;

(b) The specified causes for the withholding under the terms of the subcontract; and

(c) The remedial actions the subcontractor must take in order to receive payment of the amounts withheld.

(9) Except as provided in subsection (2) of this section, this section does not limit or impair any contractual, administrative or judicial remedies otherwise available to a contractor or a subcontractor in the event of a dispute involving a contractor’s late payment or nonpayment or a subcontractor’s deficient performance or nonperformance.

(10) A contractor’s obligation to pay a late payment interest penalty to a subcontractor under the clause included in a subcontract under subsection (3) or (4) of this section is not an obligation of the contracting agency. A contract modification may not be made for the purpose of providing reimbursement of a late payment interest penalty. A cost reimbursement claim may not include any amount for reimbursement of a late payment interest penalty.

Summary
Oregon Prompt Payment Law
Article Name
Oregon Prompt Payment Law
Description
Summary of Oregon Prompt Payment requirements and laws for Oregon construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Trusted by Thousands of Oregon Contractors Like You
For Help With Prompt Payment