Commercial Construction Project by Z Constructors at

4646 Spencer Hwy

Pasadena, TX 77504

4 Active Liens 
  • Last known event: 06/14/2021
  • First known event: 09/15/2020
HomeProjectsTexasPasadena4646 Spencer Hwy

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Hw Spencer Lp

CITY

Pasadena

Job and Payment Events

06/14/2021

Mechanics Lien Filed

Active Lien 

Lien filed by Alleyton Resource Company D B A Allied Concrete

Lien filed against Gts Concrete, Hw Spencer Lp, Z Constructors

GC listed on lien: Z Constructors

Property Owner: Hw Spencer Lp

$2,037


Source: Levelset Data

05/20/2021

Mechanics Lien Filed

Active Lien 

Lien filed by A One Sprinklers And Landscpae Design | Claimant directly hired by GC

Lien filed against Hw Spencer Lp, Z Constructors Nationwide

GC listed on lien: Z Constructors Nationwide

Property Owner: Hw Spencer Lp

$29,133


Source: Levelset Data

05/14/2021

Mechanics Lien Filed

Active Lien 

Lien filed by Alleyton Resource

Lien filed against Gts Concrete, Hw Spencer Lp, Z Constructors

GC listed on lien: Z Constructors

Property Owner: Hw Spencer Lp

$1,548


Source: Levelset Data

04/28/2021

Mechanics Lien Filed

Active Lien 

Lien filed by Z Constructors

Lien filed against 7 Eleven

GC listed on lien: Z Constructors

Property Owner: 7 Eleven

$45,985


Source: Levelset Data

02/12/2021

Slow Payment Reported

Slow Payment Reported Against Bazoria, Z Constructors

Over $5,000


Source: Levelset Data

02/12/2021

Slow Payment Reported

Slow Payment Reported Against 4646 Spencer, Bazoria, Hw Spencer Lp, Z Constructors

Over $5,000


Source: Levelset Data

01/15/2021

Slow Payment Reported

Slow Payment Reported Against Bazoria, Z Constructors

Over $10,000


Source: Levelset Data

01/15/2021

Slow Payment Reported

Slow Payment Reported Against 4646 Spencer, Bazoria, Hw Spencer Lp, Z Constructors

Over $10,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against Bazoria, Z Constructors

Over $5,000


Source: Levelset Data

11/13/2020

Slow Payment Reported

Slow Payment Reported Against Spring Creek Contracting

Over $1,000


Source: Levelset Data

09/15/2020

Slow Payment Reported

Slow Payment Reported Against S Thomas Construction, Z Constructors

Less than $1,000


Source: Levelset Data

Job Tree


Lender

Unknown


Property Owner

HS

Hw Spencer Lp


General Contractor

Z Constructors Logo

Z Constructors

3.8
D

Payment Score: 48 / 100

ZC

Z Constructors Nationwide

ZC

Z Constructors


Subcontractors

Z Constructors Logo

Z Constructors

3.8
D

Payment Score: 48 / 100

S Thomas Construction Logo

S Thomas Construction

5
D

Payment Score: 28 / 100

Spring Creek Contracting Logo

Spring Creek Contracting

1.5
F

Payment Score: 23 / 100


Supplier

JI

J.PEREZ INVESTMENTS, LLC dba JPI TRUCKING

P

ParkUSA

LA

L And W Supply


Are you on this job?

Either mark yourself or add another contractor

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now