Retainage Questions

All Status
Retainage
All States
in Nevada does the 50% cap on retention only apply to public projects?...Read More
Anonymous Contractor
1 answerAdd commentJul 16, 2020
ArizonaRetainage
Repair company For water damage to my FL home wants 100% upfront for “materials.” I want to use “ retainage” as allowed to insure prompt and satisfactory completion, having read of instances where terrible issues occurred where a company received 100% then never completed the work. Any expert advice you give will be greatly appreciated ! Thank you. ...Read More
Anonymous Contractor
1 answerAdd commentJul 7, 2020
FloridaConstruction ContractRetainage
I have a lien that has had half of it paid off. I want to release one person and leave another still on the hook without affecting the person who has paid their share. Is there a way to transfer the lien and use a different piece of property or even garnishment or something?...Read More
Anonymous Architect / Engineer
2 answersAdd commentJul 14, 2020
WashingtonCollectionsLien WaiversMechanics LienRetainage
K&P Commercial Contractors is an Out-of-State contractor working on a hotel project in NC. Due to COVID our project has been delayed and we are approaching the 120 day lien filing deadline. However we still have equipment on site that we have been invoicing each month. Can this equipment be treated as "Material Provided" and extend our filing deadline?...Read More
Anonymous General Contractor
Waiting for answerAdd commentJul 14, 2020
North CarolinaConstruction ContractLien DeadlinesMechanics LienRetainage
We are sub-subs / subs in Texas (on both public and private jobs) and often wait up to a year to get paid on retainage. We file a notice of contractual retainage on time, but I'm wondering when we should file a lien or bond claim. Often times, our deadline to file a claim appears long before the job is finished and long before our customer has even billed for their retainage. What should we do in this situation? ...Read More
Anonymous Contractor
1 answerAdd commentJul 10, 2020
TexasBond ClaimsLien DeadlinesRetainage
I'm a Subcontractor working on a Large Commercial project, I finished my work on the job two months ago but haven't fully gotten paid - and my customer isn't wanting to paid. what should I do?...Read More
Anonymous Subcontractor
1 answerAdd commentJul 2, 2020
North CarolinaMechanics LienNotice of Intent to LienPay When PaidRetainageRight to Lien
How does a continuation sheet look when you bill the retainage? ...Read More
Anonymous Contractor
Waiting for answerAdd commentJul 9, 2020
IndianaRetainage
I am a contractor that finishes our potion of the job months before the end of the actual project. I have two questions 1. Do we need to bill immediately when we have finished our portion? or Bill at the end of the project 2. Can we file a Retainage Lien prior to the end of the actual project? ...Read More
Anonymous Subcontractor
1 answerAdd commentMay 1, 2020
TexasRetainage
I'm a subcontractor that performed framing on a commercial project in Texas, everything was paid except the 10% retain for issues between the owner and the general contractor. Our trade was completed and the only reason i haven't been paid is because of a disagreement between the owner and GC unrelated to my work. The retain invoice was due 12/23/2019 and i still haven't been paid. can i still file a lien on the property? owner and GC says that as soon as they come to an agreement i will get paid but it has been 5 months already and they cant seem to reach an agreement. My contract says that i am entitled to legal fees compensation if i win the case. Thanks....Read More
Anonymous Subcontractor
1 answerAdd commentMay 27, 2020
TexasRetainage
We are a manufacturer's rep for commercial HVAC equipment - meaning we purchase from the manufacturer and then ship it to a job site. We bill the mechanical contractor who ordered it from us and they do the installation (set the unit, piping, etc.) and then part of our obligation is to provide a factory authorized company to officially start up the unit, who we hire and pay as a subcontractor. Question is - when we bill the mechanical contractor for the unit, they are holding 10% retainage on our invoices. Note that we do not bill the entire amount of our sale to them (for example, if the unit is $25,000, we bill only $24,000 and leave $1,000 balance to bill when the unit has been satisfactorily started up. Do they have the right to hold this 10% of the $24,000? If not, can I get a copy of the law that addresses this? Thanks!...Read More
Anonymous Contractor
1 answerAdd commentJun 24, 2020
New YorkConstruction ContractRetainage
a second-tier subcontractor filed a lien on a property Macomb, MI. The current plan is for a check to be written directly to the lien claimant, however, 10% retainage is withheld on the project. Would releasing retainage to the lien claimant violate the Michigan Property Code? Would the owner of the property lose protection the Property Code provided by releasing the retainage?...Read More
Anonymous Contractor
1 answerAdd commentJun 24, 2020
MichiganLien ReleasesMechanics LienRetainage
The original balance on a job we did was $45,275.10. The preliminary notice was filed in a timely manner by Levelset. We have been paid everything but the retention of $4527.50. It seems "bad form" to file a stop notice because of retention, but what is the right thing to do?...Read More
Anonymous Subcontractor
1 answerAdd commentJun 19, 2020
CaliforniaRecovery OptionsRetainageStop Notice
If there are no more funds to "trap" or if the subcontractor does not send proper trapping notices, what is the maximum amount that the sub can file a lien for? 10% of it's subcontract with the general contractor? Or 10% of the general contract?...Read More
Anonymous Contractor
4 answersAdd commentJun 29, 2020
TexasMechanics LienRetainage
Is retainage allowed in Colorado if it is not included in the contract? A prime contractor is withholding 10% retainage, even though it is not part of the contract. He is then holding funds for damages to the landscape by equipment, and final funds for the equipment rental....Read More
Anonymous Contractor
1 answerAdd commentJun 29, 2020
ColoradoBack ChargesRetainage
I am a subcontractor to a mechanical contractor in Georgia. The mechanical has a large contract with a GC that is doing a project at a public College. We have completed our part of the work over three months ago and submitted for payment and got paid all but 10% of the project. The mechanical contractors contract is on going and they say that we cannot get paid until his contract is completed and he submits for payment for our retainage along with his. Is this correct or is he required to submit for our retainage since we have completed our part of the project before he submits for his retainage.? ...Read More
Anonymous Contractor
1 answerAdd commentJun 26, 2020
GeorgiaRetainage