Miller Act Questions

All Status
Miller Act
All States
We are contracted with a door manufacture under a GC on a Navy installation, and our contract is with a subcontractor of the GC, and in our contract we have standby and delay times and have over $70k in change orders for being delayed and put on standby numerous times, and the company we are contracted with is stating they don't have to pay us unless the Navy pays them, even though they agreed to our terms for the standby time were disclosed and greed out the gate and we are NOT pay hne paid, our contract is NET 30. We do have a copy of his bond on this job. Is he still liable even if the Navy or the GC don't pay him? Looking for a local attorney to have for these questions too. ...Read More
Anonymous General Contractor
Waiting for answerAdd commentApr 21, 2021
FloridaBack ChargesChange OrdersMiller ActPay ApplicationsPayment BondPayment Disputes
We are a mat'l supplier in Ca., a prelien is in place for a large job. The job is located on a US Air force base. The miller act, federal payment bond is in the general contractor's name. Is this still effective for our customer? ...Read More
Anonymous Contractor
1 answerAdd commentApr 8, 2021
CaliforniaMiller Act
I was a subcontractor on federal job and we havent been on the job site since Sept last year. Can I still do a Bond claim?...Read More
Anonymous Subcontractor
1 answerAdd commentMar 23, 2021
NevadaBond ClaimsMiller Act
I did some work at a Naval yard for a first tier sub contractor. As the work progressed the sub contractor said that I was working for the General contractor and to get my contract from them. The General said that the change orders would be coming in and the contract would be worked out. After three months we finished our work without a contract from either party. Both contractor and sub contractor refused to pay for or furnish a contract for the work that was completed satisfactory. We filed a lien in 2018 and supplied all the data to the GC. The GC, sub contractor or bonding company did not pay us any of the $69,000.00 owed. Because of not having a contract my attorney said I had no case. Now it looks like the statute of limitation has run out. Do I have any options left? ...Read More
Anonymous Subcontractor
1 answerAdd commentJan 22, 2021
TexasMiller Act
I need an attorney in the Riverside area familiar with Miller claim ....Read More
Anonymous Contractor
3 answersAdd commentNov 30, 2020
CaliforniaMiller Act
We were a subcontractor on a federal project, our client (the general contractor) hadn't paid us our final payment in now over 120 days. We just received a partial payment from them as well as a "deductive MOD" to our contract in which the deductions they are stating are not plausible. How do we proceed in getting paid? Should we file a miller act on payment bond or what legal options do we have? Thanks...Read More
Anonymous Subcontractor
2 answersAdd commentNov 5, 2020
CaliforniaBond ClaimsConstruction ContractMiller ActPayment Disputes
Are subcontractors required to provide a payment bond performing work on a federal government construction project costing $80,000.00??...Read More
Anonymous Contractor
2 answersAdd commentJul 27, 2020
New JerseyBond ClaimsConstruction ContractMiller ActPayment Bond
I was sent Bond of affidavit claim form from a surtey company. Do i need to still file a complaint with the courts? Can i get assistance even though ive already completed the administrative process and never got response? Or can i just fill out bond then deposit it with the court? If there a maximum i can seek for damages? Non judicial administrative process do i just go get judgement? Any and all help is appreciated.....Read More
Anonymous Property Owner
2 answersAdd commentSep 27, 2020
TexasBond ClaimsCoronavirusLien ReleasesMiller ActPayment BondRecovery OptionsRight to Lien
I'm a subcontractor that worked on a federal building project. Our last day on the project was 10/4/2019 but we still have not been fully paid. I used Levelset to send in a Miller Act Claim on 9/24/2020. What are the next steps we need to take to enforce our Miller Act Lien Rights?...Read More
Anonymous Subcontractor
1 answerAdd commentOct 5, 2020
CaliforniaMiller Act
we are a small electrical company doing work for a General contractor working on a Federal job at Offutt air force base. We are about 75% done with the job but are having trouble getting paid for the last couple pay apps we’ve sent in. We are waiting for 1/2 of Feb, all of March and now we’ve billed for April. The General contractor keeps making excuses and we have paid out for labor and materials out of pocket. The General contractor does not have a bond on this job but the Main contractor Dyncorp out of Texas does have a bond and they are the ones that pay the general we are working with....Read More
Anonymous Contractor
3 answersAdd commentMay 7, 2020
NebraskaBond ClaimsMiller ActPayment BondRecovery Options
We were working on a project until we were put on hold on April 2019 and have not worked on it at all but the project wasn't cancelled until June 2020. Which date should we use for the notice of intent to lien? This is for a project on a military base in Nevada....Read More
Anonymous Sub-Subcontractor
2 answersAdd commentAug 25, 2020
NevadaBond ClaimsMiller Act
I am working on a Federal Project in Texas. We had to leave the project on May 14, 2020 due to covid. We have no idea when we can return. I have not been paid since March. My question is, does my 90 days for the Miller Act start from the last day I was there, on from when I complete the project?...Read More
Anonymous Contractor
1 answerAdd commentAug 13, 2020
TexasBond ClaimsMiller Act
I need to file a lien on a car for work I did . Will I be able to get a title to the car...Read More
Anonymous Contractor
Waiting for answerAdd commentAug 5, 2020
North CarolinaBankruptcyMiller Act
I am new here and I see that in the past they didn't send notice to bonding company. I'm thinking they should know as well that we are a contractor potentially requesting their assistance. Am I correct?...Read More
Anonymous Contractor
2 answersAdd commentJul 10, 2020
CaliforniaMiller ActPreliminary Notice
I'm a construction contractor and I have a customer that owed me $49,000 for work performed on a project. My customer received an email from a scammer pretending to be a representative of my company and asked the customer to ACH the payment to a fraudulent bank account. My customer ACH'd the payment to the fraudster. Does the customer still have to pay me? A few more related bullet points: • A conditional waiver was signed by one of my employees related to the payment • We never received the payment • My AR employee didn't follow up on payment status until 4 months later. That's when the fraud was discovered. ...Read More
Anonymous Contractor
1 answerAdd commentJun 2, 2020
TexasBond ClaimsLien WaiversMiller ActRecovery Options