I’m a subcontractor - Wallcovering- I am owed about 3000$ on a public school- can I file a lien on project?...Read More
Anonymous Contractor
2 answersAdd commentDec 28, 2020
Oklahoma
I am a subcontractor who performed work in Oklahoma under the assumption the GC I was working for would be issuing my company a change order to our contract for extra work my company performed. GC has gone quiet and has not issued said change order. We have reached out multiple times to inquire about this missing change order and received no response. ...Read More
Heather Chase
1 answerAdd commentSep 19, 2022
OklahomaChange Orders
I worked for a general contractor for 8 months but he never paid my first weeks pay. Can I lien the project I was working on ?...Read More
Anonymous Contractor
1 answerAdd commentSep 12, 2022
Oklahoma
Does the clock start over when you do touch on a project?...Read More
Anonymous Subcontractor
1 answerAdd commentApr 24, 2020
OklahomaLien Deadlines
Been 90 days getting told different things about payment. I think we are past the notice of intent ?...Read More
John Land
1 answerAdd commentSep 8, 2022
Oklahoma
My Company is a US based company with a potential customer and projects in Canada. How do I secure our lien rights in this situation? ...Read More
Tessa Booth
1 answerAdd commentJan 14, 2022
OklahomaCanadaRight to Lien
I'm a subcontractor that was working on a job in Oklahoma. We left the job because we had multiple invoices that had not been paid. The Subcontractor that we were under said they had placed a claim on the bond of the contractor. This was back in March and our deadline to place a lien on the property is now 2 week expired. What are our options to help get paid? The last day the guys where on the job was back in February. They owe us $60k+ plus late fees. ...Read More
Anonymous Contractor
1 answerAdd commentMay 26, 2022
OklahomaBond ClaimsMechanics Lien
I am a landscape contractor. I did a job without a contract, just verbal agreement. The agreement was to do the job for $8500 and lighting for $1000. I know I told him it would be hard to have much lighting for $1000. I did tell him I do not bid jobs of the unknown problems. I am sure he heard what he wanted to hear. But that I thought I could do it for $8500. At the first day or two of the job, we encountered difficulties that I knew would make it hard to get thing done within $8500. I did not mention anything at that time about how many hours we worked. We continued on the job. And the cost was about $5330. But the labor ran us over 162 hours and that tallies more than $8500. Then the lighting materials were about $1000. But the installation cost more. Near the end the client ask for some trees. I take his wife to my wholesale nursery and we buy $1735 worth of trees. I never talked about landscape stock until this late in the job . We have to move these trees with a bob cat and tree carts . We even transplant a tree . And need soil, compost , fertilizer and mulch. He sent a certified check for $8500 and another $1735 stating trees and landscape paid in full. However , the materials alone cost me more. I can’t even cover the cost of material s and labor. I am in debt $10000. Should I file a mechanic’s lien with success of getting enough money to recover?...Read More
Anonymous Contractor
2 answersAdd commentAug 1, 2022
OklahomaMechanics Lien
We worked on building Shop at McAlester with Embree Group, Inc. We have not received payment for retainage $30,984.26 ...Read More
Anonymous Subcontractor
1 answerAdd commentMay 26, 2022
OklahomaConstruction ContractRetainage
I have done some for a company/ individual who flip houses. I provided my estimate and he agreed to it. He wanted me to get done with my part in 3weeks. I responded by telling him more like 4weeks to complete my portion. Few days/weeks came by the scope changes, work was added and the time line was not met. Homeowner decided it’ll be the best for us to part ways which I than agreed. We agreed on settled amount, than he decided to even lower it, in which I was not comfortable with. Can I put a lien on the property and what happen once I do? ...Read More
Anonymous Subcontractor
Waiting for answerAdd commentMay 17, 2022
Oklahoma
I've filed a lien on a residential(non-owner occupied) property in Tulsa County, OK. What is the next step, if the debt remains unpaid? The debt owed is $2350.00 and the property owner is trying to get the Tulsa Housing Authority(section8/HUD) to approve the home as subsidized housing, for his ex-wife, who he purchased the home for in 2013. We had a written contract, sent via email to the owner(he resides in Thailand) he did not sign the contract, but did send the deposit money, as is required in the contract. ...Read More
Anonymous General Contractor
3 answersAdd commentApr 18, 2022
OklahomaLien ForeclosureMechanics Lien
Contractor did work and have been paying him over time as I do not have the funds. He is now charging me late fees and some are as high as 40% per year on the amount owed as he has miscalculated the amounts. Are there any remedies available to me? Thanks....Read More
Anonymous Contractor
1 answerAdd commentJan 29, 2022
OklahomaPrompt Payment
I have filed the lien but now I need an affordable good attorney to represent my case. ...Read More
Anonymous Contractor
1 answerAdd commentFeb 16, 2022
Oklahoma
Hello, If we filed a Mechanics Lien on a project, and now the GC for the project is advising us that the subcontractor has a payment and performance bond & is requesting us to file a bond claim, how does that affect the Mechanics Lien that was filed? Can we file a bond claim on top of the Mechanics Lien? We were not made aware of the subcontractor's bond until today. Thank you...Read More
Dawna Hilliker
2 answersAdd commentApr 20, 2022
OklahomaBond Claims